Last close As at 06/08/2026
GBP0.01
▲ −0.03 (−2.33%)
Market capitalisation
GBP166m
Research: Metals & Mining
Since our last note at the end of March, KEFI has appointed BCM as its preferred mining contractor and raised £7.6m in equity (supported by Konwave, Phoenix, Premier Miton, RAB and Ruffer, among others) to expedite the launch of the Tulu Kapi project. On site, it has constructed a new access road, a temporary construction camp, security camps and logistics control rooms, as well as drilling water boreholes and completing contractors’ certifiers’ inspections. New host lands have been allocated for all local residents requiring resettlement, and property surveys for compensation for Phase 1 resettlement, for a temporary construction camp, security camps and for a new access road have all been completed. This week, it announced the triggering of compensation payments to the resettling community. As a result, its
| Year end | Revenue (£m) | PBT (£m) | EPS (p) | DPS (p) | P/E (x) | Yield (%) |
|---|---|---|---|---|---|---|
| 12/23 | 0.0 | (4.6) | (0.21) | 0.00 | N/A | N/A |
| 12/24 | 0.0 | (8.9) | (0.21) | 0.00 | N/A | N/A |
| 12/25e | 0.0 | (14.6) | (0.17) | 0.00 | N/A | N/A |
| 12/26e | 0.0 | (0.9) | 0.03 | 0.00 | 17.0 | N/A |
In March, KEFI calculated an updated project NPV5 for Tulu Kapi of c
At our long-term gold price of
Tulu Kapi is located in the Oromia regional state (the biggest in the country) and in the Ghimbi/Gimbe zone of western Ethiopia, approximately 360km west of Ethiopia’s capital, Addis Ababa. Since our last note at the end of March, the company has:
While we had not anticipated its £7.6m (
It followed the announcement in May of Ethiopian Country Membership having been ratified
in the Ethiopian parliament for both the company’s project finance banks, which was
a key milestone, unlocking the final stages of project financing and enabling the
sequencing of contractual closings. As a result, KEFI’s
A Gantt chart of the project’s summary schedule and future milestones is therefore now as follows:
The project is expected to scale to c 160,000oz in the first full year of production, with potential to exceed 200,000oz annually with the contribution from the underground mine. As such, with contractual finalisation imminent, KEFI is at a key inflection point, now targeting first gold in late FY27.
The government owns all land in Ethiopia and every Ethiopian is entitled to land (effectively, on a long lease) at the age of 18, although the land is allocated to the family at an earlier stage. As a result, the landscape is characterised by a large number of small landholdings and any initiative such as the development of a mining project at Tulu Kapi will require a programme of resettlement including, where appropriate, infrastructure such as roads and schools etc. The process is concluded under the auspices of the government (not least because it is not in the government’s interest to create a precedent for inflated relocation compensation) and is a common aspect of life in Ethiopia.
At Tulu Kapi, the number of households needing to be relocated is c 360, representing c 1,300 people from the mine licence area. The acting government entity is the Regional Government of Oromia, its Zonal Administration of Ghimbi and its local municipality or Wereda called Genji. Over the years, KEFI has been involved in extensive community consultation and stakeholder engagement, with the result that its Resettlement Action Plan (RAP) has been approved as part of the Mining Agreement signed between the company and the government. The first compensation package has been paid for the initial construction camp area and the community property surveys on the balance of the land have also now been completed, with some already agreed and signed off. Phase 1 payments have been triggered this week.
In negotiating the RAP, the government originally offered the villagers 17 potential site options, of which three were chosen by the villagers. The most favoured sites have evolved into those nearest Tulu Kapi in order to take advantage of the economic opportunities created by the mine.
A new access road to the site of the new kebele (smallest administrative unit or ward) has now been completed. Now that compensation is being paid, residents have a statutory 90-day time limit to relocate, which should coincide with major civil works commencing at the end of the current wet season in the October 2025 to May 2026 dry season.
In consideration of the whole RAP, the long-term livelihood restoration programme
and the community development programme, KEFI has budgeted
Commissioning at Tulu Kapi is still anticipated to commence in late 2026, albeit first gold is now anticipated by the company in late FY27, rather than our assumption of early FY27 previously. Thereafter, our operational assumptions are shown in Exhibit 2. In formulating our forecasts, we have brought our mine plan as closely as possible into line with the detailed technical and financial information disclosed on KEFI’s website, at https://www.kefi-goldandcopper.com/projects/ethiopia/tulu-kapi. Edison’s assumptions and modelling are based on the original definitive feasibility study (DFS) plus a number of intervening iterations. However, they differ from KEFI’s in that the company’s mine plan includes an initial contribution from the underground mine, whereas Edison’s ‘base case’ assumptions consider the open pit, with the option to bring an underground mine plan into production only in FY29 (however this is considered in our ‘Sensitivities’ section, below).
KEFI’s proposed mining method and equipment specification at Tulu Kapi are considered straightforward and technically sound by the lenders’ independent technical expert. Within this context, it is significant that less than 10% of the total material movement is categorised as ‘selective’ under the draft mining contract specifications, indicating that the mining methods to be used are generally very standardised.
Additional costs include a 7% government mining royalty,
At the corporate level, we continue to assume head office costs of £1.0m per year
(unchanged). A carried-forward tax loss of
Our pre-production capex estimate (excluding financial items) remains unchanged at
KEFI’s approach to its funding requirements has been consistent in seeking to share risk with contractors and to minimise dilution. During 2014 and 2015, it revised its inherited DFS as a precursor to opening project construction and mining to international tender, with the specific intent of reducing upfront capex by introducing contract mining. Since then, it has introduced project-level equity (eg the government of Ethiopia and a consortium of Ethiopian investors) as well as senior secured debt provided by banks that are already working in Ethiopia, committed to the country and familiar with local market conditions and many of Tulu Kapi’s stakeholders. In this case, the adoption of senior secured debt is considered to be more compatible with Tulu Kapi’s consortium of financiers than other forms of finance. It is also anticipated to result in material savings in the cost of debt servicing, administration and other charges, especially during the project’s development and start-up period. As such, the development capital requirement of KEFI’s Ethiopian subsidiary is anticipated to be financed largely at the project level, approximately as follows:
In late 2023, Ethiopia’s central bank issued a directive exempting certain strategic
industries – including mining – from foreign exchange controls, which satisfied the
last major condition precedent for the issuance of final approval by the project finance
lenders. Since then, the secured lenders for the project have updated terms and conditions
relating to the
In the meantime, equity-capital preparations at subsidiary-company levels are advancing in line with the timetable, with government investment proceeding as planned and specialist African investors assembling for the product offering of the KEFI Minerals preference shares, which are denominated as a local-currency investment, but offer US dollar-linked protection for both principal and yield along with gold upside participation.
Otherwise, the government’s policy directive requiring a maximum 50% debt gearing
(defined as debt/[debt+equity]) for new projects has been waived in the case of Tulu
Kapi, which has prior approval to expand the debt portion of its funding requirement
to 80% of the total. In addition, clarification received from the regulator (the National
Bank of Ethiopia) indicates that historical exploration spend on the project of c
For the purposes of our valuation (below), Edison has assumed that KEFI will maintain
its 15% interest in GMCO until such time that we become aware of the terms of any
sale of its interest. In the absence of further information, we assume that its aggregate
equity contribution of c
In March 2025, KEFI calculated an updated project NPV5 for Tulu Kapi of c
Note that our risk-adjusted valuation factors, of 30.9% of enterprise value (EV) for a project at bankable feasibility stage (BFS) stage of development, 9.9% for a project at PFS stage of development and 11.7% for a project at preliminary economic assessment (PEA) stage of development, are derived from our report Gold stars and black holes (see Exhibit 166 on page 82), published in January 2019. Post-funding, these risk-adjusted NPVs may be expected to jump materially. Pre-production, they should be expected to jump materially again.
Edison’s valuation of single asset mining companies at pre-production stage is typically based on the value of dividends that a shareholder could expect to earn from their investment if they were to hold their shares from the moment of purchase until the end of the life of the mine, discounted to present value. Discretionary exploration investment is ordinarily excluded from the financial forecasts when this method is used, as it is presumed to be at least value adding. In practice therefore, the dividends in question are ‘maximum potential dividends’ (subject to assumptions about precious metals prices and the discount rate being applied). However, the resulting net present value should be considered a conservative valuation since it omits the optionality of blue-sky exploration success during the operation of the mine. This method was typically used to value South African mines that were listed in London, such as Driefontein, Kloof, Vaal Reefs, Beatrix and Western Deep Levels etc (albeit with different accounting practices), prior to 1995 when the South African mining house system of mine financing and development began to change.
Compared with the alternative discounted cash flow (DCF) method of analysis, it more purely reflects the returns that an equity shareholder may expect to receive. Hence, it is possible to calculate an internal rate of return (IRR) pertaining to an investment in a company’s equity at any particular price and any particular point in time, rather than calculating an IRR for a project as a whole (which typically aggregates debt and equity returns and is therefore independent of a company’s share price). In its application it can also be made to naturally accommodate future equity dilution in calculating returns to shareholders. Being based on only one unit of measurement (forecast future dividends), its manipulation to estimate a value (and hence share price) at some point in the future is also relatively simple in comparison with a DCF valuation, which typically requires three inputs (namely, forecast future cash flows, net debt/cash and minority ownership). In theory though, the difference between the result of a discounted dividend valuation and that of a DCF valuation should not be large. Both are provided in our valuations below.
Within the context of our valuation of KEFI, it is worth noting that the company’s financing arrangements will leave it with zero debt at the parent company level, with group subsidiaries directly servicing any senior and/or mezzanine debt. As a result, dividends to KEFI shareholders from as early as FY28 should be possible. For these purposes, we have assumed KEFI will distribute 60% of group cash flow in FY28–32, of which 80% (less a 10% Ethiopian dividend withholding tax) will be attributable to KEFI shareholders. To this end, KEFI has secured a special exemption from exchange controls from Ethiopia and has agreed a London clearing account controlled by its TKGM operating subsidiary (note: there are no exchange controls in Saudi Arabia).
Based on our unchanged long-term gold price assumptions (albeit updated to reflect real 2025 money), we calculate that all three of its projects are capable of generating a combined free cash flow to KEFI of c £99.4m per year for six years, from 2029 to 2034 (inclusive). This, in turn, will allow average (maximum potential) dividends of 0.54p/share for the period FY30–34 to be paid to shareholders (after deduction of a presumed 20% minority interest) and implies a valuation for KEFI of 1.65p/share (cf 2.03p/share previously) when discounted back to FY25 at Edison’s customary rate of 10% per year. This valuation then rises to a peak of 2.29p/share on the cusp of KEFI’s first (assumed) material dividend in FY29, as shown below:
Our estimate of KEFI’s peak earnings of 0.88p/share in FY34 would put it on a P/E ratio of just 1.1x in that year (relative to its valuation in the same year) or 0.6x at its current share price. Hence, we estimate that an investment in KEFI shares in FY25 at a price of 0.536p will generate an IRR for investors of 33.7% over the next 12 years to 2037 in sterling terms.
Note that our equivalent DCF valuation of KEFI (including forecast FY24 year-end net debt) is 1.52p/share – conducted at a similar 10% discount rate – which is within 10% of our discounted dividend valuation of 1.65p/share. This is as expected, given that the discount rate applied to a DCF valuation should be lower than that for a discounted dividend valuation, given that the former’s cash flows relate to combined debt and equity financing, whereas the latter’s relate to equity financing only and the cost of debt should typically be at a discount to that of equity.
A summary of the major factors in the change to our ‘base case’ valuation is as follows:
Quantitatively, KEFI’s most significant valuation sensitivity is towards the gold
price. Whereas our valuation is 1.65p at Edison’s long-term gold price of
In this case, we estimate that an investment in KEFI shares in FY25 at a price of 0.536p would generate an IRR for investors of 66.7% over the next 12 years to 2037 in sterling terms. Note that the dividend spike in FY33 in Exhibit 7, above, is a direct consequence of management’s assumed policy of paying out 60% of cash flow in dividends up to that point in time, thus building up a cash balance, which is then released in FY33 when total distributable funds are paid out (NB this also has the unintended consequence of depressing the valuation of the shares).
KEFI’s business plan is also to access the underground deposit at Tulu Kapi as quickly
as possible and it has PEA level plans to this effect, making a contribution to the
combined operation at a steady-state rate of c 50koz per year. For the purposes of
this note, Edison has ignored any contribution from the underground mine to its valuation,
choosing instead to focus on the initial open pit. If it is included from FY29 with
an operating cash cost of
At prevailing metals prices, it increases our valuation by 13.7%, or 0.75p/share, from 5.46p/share to 6.21p/share.
As is typical for exploration companies, KEFI has funded its pre-development activities with regular equity raisings. It had £0.6m in net debt on its balance sheet as at 31 December 2024 (cf £2.0m as at 30 June 2024 and £1.9m as at 31 December 2023), after £6.8m in operating and investing cash outflows and after having raised £4.4m (net) in equity. To date in FY25, we estimate that it has raised a further £12.7m (gross) in equity to fund development plans and also to strengthen its balance sheet.
Hereafter, we expect the government of Ethiopia to subscribe its
On the asset side of KEFI’s balance sheet, we note that the debt:equity ratio of development
spending is approximately 90.6% in the form of debt (
General disclaimer and copyright
This report has been commissioned by KEFI Gold and Copper and prepared and issued by Edison, in consideration of a fee payable by KEFI Gold and Copper. Edison Investment Research standard fees are £60,000 pa for the production and broad dissemination of a detailed note (Outlook) following by regular (typically quarterly) update notes. Fees are paid upfront in cash without recourse. Edison may seek additional fees for the provision of roadshows and related IR services for the client but does not get remunerated for any investment banking services. We never take payment in stock, options or warrants for any of our services.
Accuracy of content: All information used in the publication of this report has been compiled from publicly available sources that are believed to be reliable, however we do not guarantee the accuracy or completeness of this report and have not sought for this information to be independently verified. Opinions contained in this report represent those of the research department of Edison at the time of publication. Forward-looking information or statements in this report contain information that is based on assumptions, forecasts of future results, estimates of amounts not yet determinable, and therefore involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of their subject matter to be materially different from current expectations.
Exclusion of Liability: To the fullest extent allowed by law, Edison shall not be liable for any direct, indirect or consequential losses, loss of profits, damages, costs or expenses incurred or suffered by you arising out or in connection with the access to, use of or reliance on any information contained on this note.
No personalised advice: The information that we provide should not be construed in any manner whatsoever as, personalised advice. Also, the information provided by us should not be construed by any subscriber or prospective subscriber as Edison’s solicitation to effect, or attempt to effect, any transaction in a security. The securities described in the report may not be eligible for sale in all jurisdictions or to certain categories of investors.
Investment in securities mentioned: Edison has a restrictive policy relating to personal dealing and conflicts of interest. Edison Group does not conduct any investment business and, accordingly, does not itself hold any positions in the securities mentioned in this report. However, the respective directors, officers, employees and contractors of Edison may have a position in any or related securities mentioned in this report, subject to Edison's policies on personal dealing and conflicts of interest.
Copyright 2025 Edison Investment Research Limited (Edison).
Australia
Edison Investment Research Pty Ltd (Edison AU) is the Australian subsidiary of Edison. Edison AU is a Corporate Authorised Representative (1252501) of Crown Wealth Group Pty Ltd who holds an Australian Financial Services Licence (Number: 494274). This research is issued in Australia by Edison AU and any access to it, is intended only for "wholesale clients" within the meaning of the Corporations Act 2001 of Australia. Any advice given by Edison AU is general advice only and does not take into account your personal circumstances, needs or objectives. You should, before acting on this advice, consider the appropriateness of the advice, having regard to your objectives, financial situation and needs. If our advice relates to the acquisition, or possible acquisition, of a particular financial product you should read any relevant Product Disclosure Statement or like instrument.
New Zealand
The research in this document is intended for New Zealand resident professional financial advisers or brokers (for use in their roles as financial advisers or brokers) and habitual investors who are “wholesale clients” for the purpose of the Financial Advisers Act 2008 (FAA) (as described in sections 5(c) (1)(a), (b) and (c) of the FAA). This is not a solicitation or inducement to buy, sell, subscribe, or underwrite any securities mentioned or in the topic of this document. For the purpose of the FAA, the content of this report is of a general nature, is intended as a source of general information only and is not intended to constitute a recommendation or opinion in relation to acquiring or disposing (including refraining from acquiring or disposing) of securities. The distribution of this document is not a “personalised service” and, to the extent that it contains any financial advice, is intended only as a “class service” provided by Edison within the meaning of the FAA (i.e. without taking into account the particular financial situation or goals of any person). As such, it should not be relied upon in making an investment decision.
United Kingdom
This document is prepared and provided by Edison for information purposes only and should not be construed as an offer or sol icitation for investment in any securities mentioned or in the topic of this document. A marketing communication under FCA Rules, this document has not been prepared in accordance with the legal requirements designed to promote the independence of investment research and is not subject to any prohibition on dealing ahead of the dissemination of investment research.
This Communication is being distributed in the United Kingdom and is directed only at (i) persons having professional experience in matters relating to investments, i.e. investment professionals within the meaning of Article 19(5) of the Financial Services and Markets Act 2000 (Financial Promotion) Order 2005, as amended (the "FPO") (ii) high net-worth companies, unincorporated associations or other bodies within the meaning of Article 49 of the FPO and (iii) persons to whom it is otherwise lawful to distribute it. The investment or investment activity to which this document relates is available only to such persons. It is not intended that this document be distributed or passed on, directly or indirectly, to any other class of persons and in any event and under no circumstances should persons of any other description rely on or act upon the contents of this document.
This Communication is being supplied to you solely for your information and may not be reproduced by, further distributed to or published in whole or in part by, any other person.
United States
Edison relies upon the "publishers' exclusion" from the definition of investment adviser under Section 202(a)(11) of the Investment Advisers Act of 1940 and corresponding state securities laws. This report is a bona fide publication of general and regular circulation offering impersonal investment-related advice, not tailored to a specific investment portfolio or the needs of current and/or prospective subscribers. As such, Edison does not offer or provide personal advice and the research provided is for informational purposes only. No mention of a particular security in this report constitutes a recommendation to buy, sell or hold that or any security, or that any particular security, portfolio of securities, transaction or investment strategy is suitable for any specific person.
London │ New York │ Frankfurt
20 Red Lion Street
London, WC1R 4PS
United Kingdom
Research: Healthcare
Cereno Scientific reported positive Phase I readouts for CS014, its novel HDAC inhibitor, paving the way for Phase II studies in idiopathic pulmonary fibrosis (IPF). The candidate demonstrated favourable safety and tolerability in healthy volunteers and no serious treatment-related adverse events (all were mild and transient). Notably, CS014 achieved plasma levels exceeding the projected threshold required for reverse remodelling of pulmonary vascular and fibrosis, supporting its disease-modifying potential. Given the top-line readouts, we expect the Phase II initiation plans to stay on track for H126, with potential partnering discussions in the interim. We raise our probability of success (PoS) for CS014 to 20% (10% previously), resulting in our valuation upgrading to SEK5.0bn or SEK17.7 per share (from SEK4.5bn or SEK16.0 per share previously).