While Barberton outperformed our expectations (owing to an improvement in output at
all operations in the wake of its restructuring and 20% workforce reduction), it was
offset by a shortfall at Evander (due to a slower than expected ramp up after the
commissioning of the subvertical shaft in January), while Nobles missed what was otherwise
a relatively aggressive production target.
Since the completion of its commissioning, however, the sub-vertical shaft’s full
700t/day hoisting capacity at Evander has become available since April. In combination
with the establishment of the high-grade 24 Level B-Line raise in Q325, face length
and mining flexibility have therefore improved to such an extent that output should
average c 3,850oz pm in May and June (46,200oz per year annualised).
In the meantime, at Barberton, high-grade areas of the 262 Platform at Fairview Mine,
indicated by drill intersections of up to 80g/t Au, have been accessed, while underground
sampling at Consort has confirmed high-grade mineral reserve areas below 41 Level
in the Prince Consort shaft area (which has now been rehabilitated).
Concurrently, in Australia, construction at Tennant Mines’ Nobles operation (at a
cost of
US$36m) was completed with successful hot commissioning in April. After an inaugural gold
pour in May, however, production ramp up was slower than expected owing to a delay
in the commissioning of the filter presses associated with the dry stack landforms
(required for tailings deposition). Nevertheless, steady-state throughput at an annualised
rate of c 50,000oz per year is still expected to be
achieved in Q126.
While production in FY25 was c 4.2% below our expectations (outlined in our note of 25 April), the gold price has comfortably outperformed our forecast
US$3,157/oz ‘for the remainder of the financial year’, averaging
US$3,223/oz in April,
US$3,289/oz in May and
US$3,361/oz so far in June.
In addition to changes to our immediate production and gold price assumptions, we
have also revised our estimate of forex rates to reflect the recent (slightly unusual)
strength of the rand against both the US dollar and sterling:
- from ZAR25.3436/£ to ZAR24.1513/£ (-4.7%),
- from ZAR19.3243/US$ to ZAR17.7650/US$ (-8.1%), and
- from
US$1.3115/£ to
US$1.3596/£ (+3.7%).
In tandem with its updated cost guidance, we have therefore revised our operational
forecasts for Pan African’s mines for H225 to those shown in Exhibit 2 below.