Perfecting the Soweto Cluster
On 27 November, Pan African announced that it had completed two studies to process
its Soweto tailings storage facilities (TSFs) near to the MTR/Mogale plant:
- a 1Mtpm standalone carbon-in-leach (CIL) plant, for which a DFS was completed; and
- a 600ktpm expansion circuit to be added to the existing MTR/Mogale operation (albeit
with standalone feed from the Soweto TSFs), for which a PFS was completed.
Both of these options focus on the possibility of constructing a new, standalone processing
facility close to the MTR/Mogale plant, but include the option to reprocess additional
proximal TSF resources that will add to the project’s life. This is in contrast to
the base-case plan modelled by Edison hitherto to feed Soweto Cluster material through
the MTR/Mogale plant once the latter’s feedstock is near exhaustion at the end of
its life, and arises from the observation that the capital cost of constructing a
standalone processing plant near the Soweto Cluster would be little more than that
required for the infrastructure to pump Soweto Cluster material to the MTR/Mogale
plant alone. Constructing a standalone plant close to MTR/Mogale also has the advantage
of locating it close to the redeposition site on land already owned by Pan African,
as well as allowing the two to share central facilities such as offices, the smelt
house etc.
Of the two, the integrated 600ktpm Soweto tailings retreatment circuit at MTR/Mogale
was identified as the preferred
option owing to its synergies with the existing MTR/Mogale plant and infrastructure
leading to a significantly lower upfront capital requirement, shorter construction
period, reduced permitting obligations and superior financial returns. As a result,
PAF’s management has advanced its option to a DFS, which is expected to be completed
by June 2026.
Highlights of the PFS completed to date on the 600ktpm option are as follows:
- Anticipated construction period of approximately 24 months.
- Capital cost of c
US$160m (approximately ZAR2.8bn at a foreign exchange rate of ZAR17.50/
US$), which includes re-mining and overland pumping infrastructure and expanded TSFs.
- Expected annual gold production of 30–35koz for approximately 15 years at an ASIC
of
US$1,000–1,200/oz.
At a gold price of
US$2,800/oz, the PFS calculated that the project returns:
- A post-tax NPV of
US$129.7m (ZAR2,270m), or 6.4 US cents per share (ZAR1.12 per share) at a relatively elevated
discount rate of 13.3%.
- A real, ungeared internal rate of return (IRR) of 29.4%.
- A payback period of three years (post-commissioning).
At a gold price of
US$3,500/oz, the PFS calculated that the project returns:
- A post-tax NPV13.3 of
US$235.4m (ZAR4,120m), or 11.6 US cents per share (ZAR2.03 per share).
- A real, ungeared IRR of 40.2%.
- A payback of two years (post-commissioning).
A final board decision on the project is expected shortly after the completion of
the 600ktpm option DFS in mid-CY26 (end-FY26). After two years of construction therefore,
commissioning of the plant could occur as early as mid-CY28 (start-FY29).
Separately, Pan African announced that it was continuing to optimise operations at
MTR/Mogale, with the goal of expanding the plant from 800ktpm to 1Mtpm via the addition
of two CIL tanks, together with the installation of reactors to further improve recoveries
for a capital cost of c
US$6.5m. This will result in an increase in production from 50,000oz to c 60,000oz per year
from FY26. The optimisation is expected to be completed later this month (December).
To date, Edison has already anticipated this expansion in its financial modelling.
However, the PFS on the 600ktpm option at Soweto represents a marked acceleration
of the project at scale relative to our earlier expectations, which were previously
aligned with the production profile set out most recently on slide 18 of PAF’s FY26 results presentation.
Precise details relating to the 600ktpm option are, as yet, unavailable. However,
we have now updated our production and financial model of the Soweto Cluster to reflect
as many details as possible of the announcement and to recognise that this is now
management’s preferred option. Clearly, the main development, relative to our prior
expectations, is the acceleration of production. Whereas this was originally intended
to be complementary to production from MTR/Mogale for the first eight years of operations,
before being scaled up to full capacity in FY38, it will now be brought in at higher
levels earlier, without the need for a significant expansion and significant interim
capital expenditure: