Last close As at 05/08/2026
GBP1.02
▲ −2.10 (−2.02%)
Market capitalisation
GBP2,539m
Research: Metals & Mining
Pan African Resources’ (PAF’s) FY24 results, announced on 11 September, were within 1% of our prior forecasts for both EPS (4.14c cf 4.17c) and headline EPS (HEPS; 4.15c cf 4.17c). However, if the contract liability related to its ZAR400m financing facility for Mintails is stripped out, we calculate that PAF would have recorded HEPS of 5.27c, which would have been close to the top of the range of analysts’ expectations and also a record for both 12-month and six-month periods. While arguably academic for FY24, this nevertheless sets the stage for more material EPS and cash flow increases in the future as the Mintails contract liability concludes in February 2025 at the same time that opex stabilises and capex begins to fall away.
Pan African Resources |
Analysing H224 and looking forward to FY25 |
FY24 results |
Metals and mining |
27 September 2024 |
Share price performance
Business description
Next events
Analyst
Pan African Resources is a research client of Edison Investment Research Limited |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Pan African Resources’ (PAF’s) FY24 results, announced on 11 September, were within 1% of our prior forecasts for both EPS (4.14c cf 4.17c) and headline EPS (HEPS; 4.15c cf 4.17c). However, if the contract liability related to its ZAR400m financing facility for Mintails is stripped out, we calculate that PAF would have recorded HEPS of 5.27c, which would have been close to the top of the range of analysts’ expectations and also a record for both 12-month and six-month periods. While arguably academic for FY24, this nevertheless sets the stage for more material EPS and cash flow increases in the future as the Mintails contract liability concludes in February 2025 at the same time that opex stabilises and capex begins to fall away.
Year end |
Revenue (US$m) |
PBT* |
EPS* |
DPS |
P/E |
Yield |
06/23** |
321.6 |
92.9 |
3.54 |
0.95 |
12.6 |
2.1 |
06/24*** |
373.8 |
119.8 |
4.68 |
1.26 |
9.5 |
2.8 |
06/25e |
459.3 |
182.6 |
7.28 |
1.49 |
6.1 |
3.3 |
06/26e |
477.3 |
169.3 |
6.71 |
5.16 |
6.7 |
11.6 |
Note: *PBT and EPS are normalised, excluding amortisation of acquired intangibles and exceptional items. **FY23 not restated. ***FY24 ‘as reported’ not ‘adjusted’ (see Exhibit 4).
Higher production presages higher dividends
As well as increased earnings, PAF increased its dividend for the first time in four years in FY24 and set a target of paying out 40–50% of net cash generated from operating activities to shareholders. As a result, we believe that materially increased dividend payouts are possible in the coming years. Our forecasts are currently in the middle of the range of analysts’ expectations for FY25, but at the top of the range for FY26. If achieved, however, we calculate that PAF would almost certainly have the second highest dividend yield of the 62 precious metals mining companies expected to pay dividends to shareholders globally over the next 12–24 months.
Valuation: Still cheap compared to history and peers
We have pared back our core (absolute) valuation of PAF to its pre-May level of 40.93c per share (31.82p) to reflect both the recent, slightly uncharacteristic ‘above trend’ strength of the rand against both the US dollar and sterling and slightly sticky cost inflation in H224. However, this valuation rises by a further 22.30–27.32c if other assets (eg Egoli and the Soweto cluster) are taken into account. Alternatively, if PAF’s historical average price to normalised HEPS ratio of 8.2x for the period FY10–24 is applied to our FY25 and FY26 forecasts, it implies a value of 44.70p in FY25, followed by 41.17p in FY26. As such, PAF’s current share price of 33.65p could be interpreted as discounting normalised HEPS rising to only 5.48c per share in FY25 and/or FY26 (cf our forecasts of 7.28c and 6.71c, respectively). In the meantime, PAF remains cheaper than its principal London- and South African-listed gold mining peers on at least 80% of commonly used valuation measures, regardless of whether they are based on Edison or consensus forecasts. Performing a relative valuation analysis, its peers imply a comparable valuation for PAF of 61.03p based on our year one EPS estimate and 43.33p based on our year two EPS estimate. Finally, we calculate that PAF is trading at an enterprise value of just US$23.33 per resource ounce of gold.
FY24 and H224 results
PAF’s FY24 results, announced on 11 September, were closely in line with our forecasts for headline EPS (HEPS) and EPS and also guidance, as provided in its announcements of 29 July and 5 September.
Production in H224 was confirmed at 87,581oz, representing a 5.6% increase compared with H223, while guidance for FY25 was reiterated at 215–225koz at an all-in sustaining cost (AISC) of US$1,350–1,400/oz – not more than 3.4% higher than during FY24 – albeit with the proviso that ‘the delay in the commissioning of Evander Mines’ subvertical shaft, scheduled to be completed during September 2024, could impact guidance by approximately 5,000oz’. Exhibit 1, below, shows Pan African’s group production in H224 compared to H223 and H124, and also our forecast for a further 12.1% output growth in FY25.
Exhibit 1: Pan African production, H121–FY25e (oz)
Operation |
H121 |
H221 |
H122 |
H222 |
H123 |
H223 |
H124 |
H224 |
Change* (%) |
Change** (oz) |
FY24 |
FY25e |
Growth (%) |
Barberton UG |
42,350 |
42,476 |
39,991 |
35,747 |
32,022 |
32,564 |
36,780 |
34,690 |
+6.5 |
-5.7 |
71,470 |
79,235 |
+10.7 |
BTRP |
10,004 |
8,235 |
9,126 |
10,434 |
10,012 |
9,863 |
9,864 |
9,024 |
-8.5 |
-8.5 |
18,888 |
13,913 |
-26.3 |
Barberton |
52,354 |
50,711 |
49,117 |
46,181 |
42,034 |
42,427 |
46,644 |
43,714 |
+3.0 |
-6.3 |
90,358 |
93,148 |
+3.1 |
Evander UG |
12,607 |
23,409 |
27,312 |
21,538 |
19,173 |
10,359 |
21,307 |
16,978 |
+63.9 |
-20.3 |
38,285 |
42,042 |
+9.8 |
Evander surface |
6,560 |
4,677 |
5,756 |
3,564 |
5,270 |
5,373 |
2,401 |
183 |
-96.6 |
-92.4 |
2,584 |
0 |
-100.0 |
Evander |
19,169 |
28,086 |
33,068 |
25,102 |
24,443 |
15,732 |
23,708 |
17,161 |
+9.1 |
-27.6 |
40,869 |
42,042 |
+2.9 |
Elikhulu |
26,863 |
24,596 |
25,900 |
26,320 |
25,830 |
24,743 |
28,106 |
26,706 |
+7.9 |
-5.0 |
54,812 |
49,143 |
-10.3 |
MTR |
24,127 |
N/A |
|||||||||||
Total |
98,386 |
103,391 |
108,085 |
97,603 |
92,307 |
82,902 |
98,458 |
87,581 |
+5.6 |
-11.0 |
186,039 |
208,460 |
+12.1 |
Source: Edison Investment Research, Pan African Resources. Note: Totals may not add up owing to rounding. UG, underground. BTRP, Barberton Tailings Retreatment Project. *H224 cf H223. **H224 cf H124.
Output for each of PAF’s four producing operations in H224 was exactly in line with guidance, with the exception of a tiny amount of production (183oz) from surface sources at Evander. However, with the exception of the Barberton Tailings Retreatment Project (BTRP) that output was generally achieved via processing slightly higher volumes of tonnage at slightly lower grades than we had anticipated. In the case of the BTRP, both tonnage and grade were lower than our prior expectations, but were offset by the highest metallurgical recoveries since H116, as shown below:
Exhibit 2: PAF mines* operational statistics, H224a cf H224e
Barberton |
Elikhulu |
Evander |
BTRP |
Total |
||||||
H224e (prior) |
H224a |
H224e (prior) |
H224a |
H224e (prior) |
H224a |
H224e (prior) |
H224a |
H224e (prior) |
H224a |
|
Total tons milled (t) |
173,650 |
178,163 |
6,971,392 |
7,029,072 |
71,586 |
102,400 |
431,442 |
395,805 |
7,652,947 |
7,707,930 |
Head grade (g/t) |
6.72 |
6.51 |
0.34 |
0.34 |
7.56 |
5.71 |
1.54 |
1.28 |
0.62 |
0.60 |
Contained gold (oz) |
37,507 |
37,267 |
76,280 |
76,303 |
17,410 |
18,786 |
21,384 |
16,297 |
152,761 |
148,794 |
Recovery (%) |
92.5 |
93.1 |
35.0 |
35.0 |
98.0 |
90.4 |
42.2 |
55.4 |
57.3 |
58.9 |
Production (oz) |
34,690 |
34,690 |
26,706 |
26,706 |
17,062 |
16,978 |
9,024 |
9,024 |
87,581 |
87,581 |
Production – other (oz) |
||||||||||
Total production (oz) |
34,690 |
34,690 |
26,706 |
26,706 |
17,062 |
16,978 |
9,024 |
9,024 |
87,581 |
87,581 |
Recovered grade (g/t) |
6.21 |
6.06 |
0.12 |
0.12 |
7.41 |
5.16 |
0.65 |
0.71 |
0.36 |
0.35 |
Gold sold (oz) |
34,690 |
33,952 |
26,706 |
26,159 |
17,062 |
17,170 |
9,024 |
8,963 |
87,581 |
86,427 |
Average spot price (US$/oz) |
2,206 |
2,191 |
2,206 |
2,069 |
2,206 |
1,801 |
2,206 |
2,205 |
2,206 |
2,077 |
Average spot price (ZAR/kg) |
1,328,243 |
1,319,008 |
1,328,243 |
1,245,741 |
1,328,243 |
1,084,493 |
1,328,243 |
1,327,800 |
1,328,243 |
1,250,775 |
Total cash cost (US$/oz) |
1,412 |
1,632 |
840 |
1,000 |
1,232 |
1,336 |
679 |
691 |
1,128 |
1,297 |
Total cash cost (ZAR/kg) |
849,928 |
963,016 |
506,000 |
601,824 |
741,918 |
804,493 |
408,749 |
416,118 |
679,155 |
769,571 |
Total cash cost (US$/t) |
281.99 |
311.06 |
3.22 |
3.79 |
293.69 |
223.84 |
14.20 |
15.66 |
12.91 |
14.33 |
Total cash cost (ZAR/t) |
5,281.00 |
5,708.04 |
60.29 |
69.66 |
5,500 |
4,196 |
265.91 |
293.09 |
241.74 |
268.39 |
Implied revenue (US$000) |
76,526 |
74,377 |
58,913 |
54,122 |
37,639 |
30,926 |
19,907 |
19,766 |
193,204 |
179,507 |
Implied revenue (ZAR000) |
1,433,136 |
1,393,210 |
1,103,295 |
1,013,594 |
704,876 |
579,289 |
372,805 |
370,188 |
3,618,203 |
3,362,282 |
Implied revenue (£000) |
60,485 |
57,881 |
46,565 |
42,083 |
29,749 |
23,948 |
15,734 |
15,380 |
152,706 |
139,497 |
Implied cash costs (US$000) |
48,968 |
55,420 |
22,443 |
26,661 |
21,024 |
22,921 |
6,126 |
6,199 |
98,789 |
112,077 |
Implied cash costs (ZAR000) |
917,048 |
1,016,961 |
420,305 |
489,662 |
393,723 |
429,634 |
114,726 |
116,005 |
1,850,055 |
2,068,729 |
Implied cash costs (£000) |
38,711 |
43,139 |
17,742 |
20,675 |
16,620 |
18,127 |
4,843 |
4,897 |
78,096 |
87,517 |
Source: Pan African Resources, Edison Investment Research. Note: *Excludes Evander surface operations.
Relative to a 2.8% year-on-year increase in tonnes milled/processed and a South African inflation rate of 5.1% (June-June), Pan African’s electricity costs (14.1% of the total) increased by 66.4% during the year, while processing and metallurgical costs (21.7%) increased by 59.9% and security costs (3.2% of the total) increased by 27.7%. As a result, unit costs per tonne of ore milled/processed were higher than we had anticipated at Barberton, Elikhulu and the BTRP and, while we still expect these to moderate over time, we now expect them to moderate from a higher base. By contrast, Evander milled 14.2% more ore in H224 compared to H124 for 7.0% less cost in rand terms to result in an 18.6% lower unit cost, enviably demonstrating both economy and the benefits of incremental production on a relatively high fixed cost base. Within this context, the overall increase in the group’s AISC, from US$1,309/oz in FY23 (restated) to US$1,354/oz in FY24 – an increase of only 3.4% – was a creditable achievement.
The other noteworthy feature of the group’s results was the price of gold that PAF received for its output, which was reported as US$2,015/oz for the full year (a 3.0% discount to the average gold price of US$2,078/oz during the period) and calculated by Edison as US$2,077/oz for H224 (a 5.8% discount to the average gold price of US$2,206/oz). These discounts arise from the accounting treatment of the contract liability related to the fixed-price forward sales associated with Pan African’s ZAR400m Mintails financing facility, which is different to that relating to ‘normal’ derivatives. Derivatives are subject to mark-to-market fair value accounting, with any adjustment going through the ‘other income/expense’ line in the P&L. By contrast, fixed-price forward gold sales result in the fixed gold price for these ounces being recognised in revenue – there being no equivalent mark-to-market fair value accounting. However, synthetic forward sales of gold, which are composed of a series of options (puts and calls at the same price) are also accounted for as a ‘plain vanilla’ forward sale (and not a derivative instrument), with the fixed gold price recognised in revenue as the ounces are delivered since, despite being a derivative instrument, they are, in substance, identical to a ‘plain vanilla’ fixed price forward sale.
Exhibit 3: PAF aggregate operational results, H222–H224
H222 |
H123 |
H223 |
H124 |
H224e |
H224 |
Change* |
Variance** |
FY24 |
FY24e |
|
Total tons milled (t) |
8,104,217 |
8,024,228 |
7,235,156 |
7,974,470 |
7,652,947 |
7,707,930 |
-3.3 |
0.7 |
15,682,400 |
15,627,417 |
Head grade (g/t) |
0.65 |
0.63 |
0.66 |
0.65 |
0.62 |
0.60 |
-7.7 |
-3.2 |
0.62 |
0.63 |
Contained gold (oz) |
169,236 |
162,694 |
152,462 |
166,240 |
152,761 |
148,794 |
-10.5 |
-2.6 |
315,034 |
319,001 |
Recovery (%) |
57.7 |
56.7 |
54.4 |
59.2 |
57.3 |
58.9 |
-0.5 |
2.8 |
59.1 |
58.3 |
Production (oz) |
97,603 |
92,307 |
82,902 |
98,458 |
87,581 |
87,581 |
-11.0 |
0.0 |
186,039 |
186,039 |
Production – other (oz) |
0 |
0 |
0 |
0 |
0 |
0 |
N/A |
N/A |
0 |
0 |
Total production (oz) |
97,603 |
92,307 |
82,902 |
98,458 |
87,581 |
87,581 |
-11.0 |
0.0 |
186,039 |
186,039 |
Recovered grade (g/t) |
0.37 |
0.36 |
0.36 |
0.38 |
0.36 |
0.35 |
-7.9 |
-2.8 |
0.37 |
0.37 |
Gold sold (oz) |
98,546 |
90,439 |
84,321 |
98,458 |
87,581 |
86,427 |
-12.2 |
-1.3 |
184,885 |
186,039 |
Average spot price (US$/oz) |
1,846 |
1,725 |
1,955 |
1,961 |
2,206 |
2,077 |
5.9 |
-5.8 |
2,015 |
2,076 |
Average spot price (ZAR/kg) |
914,454 |
960,947 |
1,143,075 |
1,178,433 |
1,328,243 |
1,250,775 |
6.1 |
-5.8 |
1,212,250 |
1,248,958 |
Total cash cost (US$/oz) |
1,193 |
1,106 |
1,175 |
1,130 |
1,128 |
1,297 |
14.8 |
15.0 |
1,200 |
1,129 |
Total cash cost (ZAR/kg) |
590,888 |
616,134 |
694,824 |
678,941 |
679,155 |
769,571 |
13.3 |
13.3 |
721,293 |
679,028 |
Total cash cost (US$/t) |
14.51 |
12.47 |
13.82 |
13.95 |
12.91 |
14.33 |
2.7 |
11.0 |
14.14 |
13.44 |
Total cash cost (ZAR/t) |
223.48 |
216.00 |
251.87 |
260.72 |
241.74 |
268.39 |
2.9 |
11.0 |
264.49 |
251.43 |
Implied revenue (US$000) |
181,886 |
156,011 |
164,846 |
193,080 |
193,204 |
179,507 |
-7.0 |
-7.1 |
372,587 |
386,284 |
Implied revenue (ZAR000) |
2,802,891 |
2,703,093 |
2,997,891 |
3,608,788 |
3,618,203 |
3,362,282 |
-6.8 |
-7.1 |
6,971,070 |
7,226,990 |
Implied revenue (£000) |
140,063 |
132,685 |
133,653 |
153,972 |
152,706 |
139,497 |
-9.4 |
-8.6 |
293,468 |
306,678 |
Implied cash costs (US$000) |
117,584 |
100,488 |
99,091 |
111,222 |
98,789 |
112,077 |
0.8 |
13.5 |
223,299 |
210,011 |
Implied cash costs (ZAR000) |
1,811,131 |
1,733,195 |
1,822,284 |
2,079,082 |
1,850,055 |
2,068,729 |
-0.5 |
11.8 |
4,147,812 |
3,929,137 |
Implied cash costs (£000) |
90,375 |
85,148 |
80,881 |
88,721 |
78,096 |
87,517 |
-1.4 |
12.1 |
176,238 |
166,816 |
Source: Pan African Resources, Edison Investment Research. Note: *H224 cf H124, **H224 cf H224e. Totals may not add up owing to rounding. H123 and H223 ‘as reported’ and not restated as per FY24 results (NB restatement deemed immaterial by Edison).
By contrast, for ease of comparison, Edison forecasts revenue based on the prevailing price of gold with all derivative-type profits/losses being booked through the ‘other’ line. Although this is not strictly in accordance with accounting standards, it allows the underlying performance of the operating company to be distinguished from the volatility created by derivative-type profits and losses, which are then presented as a single line item. In the case of H224, Pan African sold 1,154 fewer ounces than it produced in H224, which cost it c US$2.5m in revenue at the average gold price during the period (albeit we would expect this figure to be recouped in coming quarters). In addition, we estimate that its Mintails financing arrangements depressed revenue by a further c US$11.1m (86,427oz sold at US$2,077/oz in H224 rather than US$2,206/oz). Adding back US$11.1m to reported revenue implies like-for-like revenue of US$191.0m in H224, compared to US$196.8m forecast and US$179.8m actually reported. Note that this adjustment, with revenue presented on a ‘plain vanilla’ basis and derivative-type losses all shown in the ‘other’ line, is shown in the column denoted ‘H224 (adjusted)’ in Exhibit 4, below. On this like-for-like basis, revenue was US$5.8m (or 1.5%) less than we had forecast for both H224 and FY24 (of which c US$2.5m could be accounted for by unsold gold), while costs were US$12.1m (or 5.8%) higher for the full year, leading to a US$17.2m (or 10.8%) negative variance in mining profits. However, this was essentially offset by an US$8.2m positive variance in ‘other’ expenses (the difference between a US$22.5m loss forecast and an underlying US$14.3m loss reported), a US$2.0m positive variance in royalty costs, a US$4.1m positive variance in net finance income and a US$1.9m positive variance in the overall tax charge to result in actual H224 and FY24 attributable profit within US$0.6m, or 1.0%, of our prior forecast.
A complete analysis of PAF’s H224 and FY24 results on both an ‘as reported’ and an ‘adjusted’ basis (with all derivative-type losses taken through the ‘other’ line) is provided in Exhibit 4, below:
Exhibit 4: PAF P&L statement by half year (H124–H224)
US$000s* |
H124 |
H224e |
H224 (as reported) |
H224 (adjusted) |
Change*** (%) |
Variance**** |
FY24 (adjusted) |
FY24 (as reported) |
FY24e |
Revenue |
193,947 |
196,763 |
179,849 |
190,998 |
-7.3 |
-2.9 |
384,945 |
373,796 |
390,710 |
Cost of production |
(110,292) |
(98,789) |
(110,891) |
(110,891) |
0.5 |
12.3 |
(221,183) |
(221,183) |
(209,081) |
Depreciation |
(10,768) |
(11,144) |
(10,476) |
(10,476) |
-2.7 |
-6.0 |
(21,244) |
(21,244) |
(21,912) |
Mining profit |
72,887 |
86,831 |
58,482 |
69,631 |
-19.8 |
-19.8 |
142,518 |
131,369 |
159,718 |
Other income/(expenses) |
(7,231) |
(22,474) |
(3,144) |
(14,293) |
-56.5 |
-36.4 |
(21,524) |
(10,375) |
(29,705) |
Loss in associate etc |
0 |
0 |
0 |
0 |
N/A |
N/A |
0 |
0 |
0 |
Loss on disposals |
0 |
0 |
0 |
0 |
N/A |
N/A |
0 |
0 |
0 |
Impairments |
0 |
0 |
0 |
0 |
N/A |
N/A |
0 |
0 |
0 |
Royalty costs |
(1,242) |
(2,465) |
(445) |
(445) |
-64.2 |
-81.9 |
(1,687) |
(1,687) |
(3,707) |
Net income before finance |
64,414 |
61,891 |
54,893 |
54,893 |
-14.8 |
-11.3 |
119,307 |
119,307 |
126,305 |
Finance income |
760 |
1,124 |
1,124 |
47.9 |
N/A |
1,884 |
1,884 |
||
Finance costs |
(5,594) |
(6,190) |
(6,190) |
10.7 |
N/A |
(11,784) |
(11,784) |
||
Net finance income |
(4,834) |
(9,201) |
(5,066) |
(5,066) |
4.8 |
-44.9 |
(9,900) |
(9,900) |
(14,035) |
Profit before taxation |
59,580 |
52,691 |
49,827 |
49,827 |
-16.4 |
-5.4 |
109,407 |
109,407 |
112,271 |
Taxation |
(17,223) |
(15,297) |
(13,358) |
(13,358) |
-22.4 |
-12.7 |
(30,581) |
(30,581) |
(32,520) |
Effective tax rate (%) |
28.9 |
29.0 |
26.8 |
26.8 |
-7.3 |
-7.6 |
28.0 |
28.0 |
29.0 |
PAT (continuing ops) |
42,357 |
37,393 |
36,469 |
36,469 |
-13.9 |
-2.5 |
78,826 |
78,826 |
79,750 |
Minority interest |
(224) |
0 |
(328) |
(328) |
46.4 |
N/A |
(552) |
(552) |
(224) |
Ditto (%) |
(0.5) |
0.0 |
(0.9) |
(0.9) |
80.0 |
N/A |
(0.7) |
(0.7) |
(0.3) |
Attributable profit |
42,581 |
37,393 |
36,797 |
36,797 |
-13.6 |
-1.6 |
79,378 |
79,378 |
79,974 |
Headline earnings |
42,581 |
37,393 |
36,903 |
36,903 |
-13.3 |
-1.3 |
79,484 |
79,484 |
79,974 |
Est. normalised headline earnings |
49,812 |
59,867 |
40,047 |
51,196 |
-19.6 |
-14.5 |
101,008 |
89,859 |
109,679 |
EPS (c) |
2.22 |
1.95 |
1.92 |
1.92 |
-13.5 |
-1.5 |
4.14 |
4.14 |
4.17 |
HEPS** (c) |
2.22 |
1.95 |
1.93 |
1.93 |
-13.1 |
-1.0 |
4.15 |
4.15 |
4.17 |
Normalised HEPS (c) |
2.60 |
3.12 |
2.09 |
2.67 |
-19.6 |
-14.4 |
5.27 |
4.68 |
5.72 |
Source: Pan African Resources, Edison Investment Research. Note: *Unless otherwise indicated. **HEPS, headline earnings per share (South African reporting standard). ***H224 cf H124. ****H224 (adjusted) cf H224e. Exhibit 19 presented on an ‘as reported’ basis.
Note that the effect of the Mintails contract liability on prior periods was small to the point of being negligible given that the contracted price of gold was close to the actual price of gold. The exclusion of US$4.1m in ‘other income’ from ‘H224 (adjusted)’ results would also have brought Edison’s forecast of a US$22.5m loss more closely into line with the US$14.3m loss imputed. Otherwise, on this comparative (ie ‘adjusted’) basis, normalised HEPS were 7.9% lower than our estimate for the full year. However, they were still nevertheless a record for Pan African for both a full-year and half-year period and well to the top end of the range of analysts’ expectations of 3.0–5.7c/share with a mean of 4.5c/share (source: LSEG Data & Analytics, 6 September 2024).
From the perspective of PAF’s four principal operations (ie excluding the negligible contribution from Evander surface sources), performance held steady at both Barberton and Elikhulu, but fell away at Evander (which is the operation most affected by the Mintails contract liability – see Exhibit 2), while the BTRP announced record adjusted EBITDA in both rand and US dollar terms:
|
Exhibit 5: Pan African adjusted EBITDA, by business unit, H115–H224 |
|
|
Source: Pan African Resources, Edison Investment Research |
Growth projects
PAF has two organic growth projects currently underway (namely the MTR project within the Mintails Soweto Cluster and the Evander 24 to 26 Level expansion project) and one more immediately in prospect (the Sheba Fault project). Beyond these, it has the Egoli and Fairview sub-vertical shaft projects at feasibility study stage followed by Rolspruit, Poplar and Evander South also available for eventual development.
Mintails Soweto Cluster
Mogale (MTR)
On 1 August 2023, PAF announced that all conditions precedent for its ZAR1.3bn senior debt facility, designated for funding the group’s MTR project, had been fulfilled, thereby completing the full upfront funding package of ZAR2.5bn. Since then, PAF has reported that construction has been progressing on time and within budget, with commissioning and steady state production still on track for December 2024.
On 9 May, PAF reported that it had updated its financial model for Mogale (relative to the initial definitive feasibility study model) to reflect the latest operating cost updates, as well as a ZAR19.00/US$ forex rate and a US$2,200/oz gold price. The result was:
■
A near threefold increase in pre-tax NPV from US$63m to US$183m (9.5c/share).
■
A doubling of the ungeared real internal rate of return from 20.1% to 41.7%.
■
A two-year payback on upfront capital investment of c US$135.1m (cf an initial DFS model estimate of 3.5 years), post commissioning.
Soweto cluster
In addition to its update on the MTR, in May PAF also announced the results of an internal pre-feasibility study (PFS) for the Soweto cluster that was completed in March 2024, based on drill results from the 2L16 and 2L24 tailings storage facilities. The PFS considered a number of options, of which the most feasible was considered to be the processing of the Soweto cluster material at the MTR plant. In this case, the MTR plant’s capacity could be expanded to process 1Mtpm of feed material (cf the current design capacity of 800ktpm) to result in a mine life of 21 years for the combined Mogale and Soweto cluster resources. The resultant tailings could then be deposited into the expanded Mogale tailings storage facility at the West Wits pit and 1L23-25 footprint.
Other specific results of the PFS were as follows:
■
The MTR plant infrastructure could be expanded to treat 1Mtpm from year six of the MTR operation’s mine life (ie approximately 2030).
■
The addition of the 110Mt Soweto cluster mineral resource has the potential to increase MTR production to approximately 60koz pa over a 21-year mine life.
■
Total additional capex for the project would be US$113m, of which c US$83m would be incurred in years 4–6 of the MTR project timeline and US$29m would be incurred in year 10 of the timeline.
■
At US$2,200/oz and a forex rate of ZAR19.00/US$, the pre-tax NPV for the combined Mogale-Soweto cluster is US$283m (or 14.8c, or 11.1p, per share), representing a >50% increase relative to the MTR project alone.
■
The real, ungeared internal rate of return of the combined project increases to 44.0% (cf 41.7% for the MTR project alone).
These changes have already been incorporated into our financial model since May. In the meantime, Pan African is proceeding with the necessary permitting and servitudes required for the re-mining and processing of the Soweto cluster, with a final investment decision anticipated ‘in due course’.
Evander 24 to 26 Level expansion project
Progress at Evander’s 24 to 26 Level underground expansion project remains on track, with the following notable achievements during H224:
■
Ramped-up mining operations on 24 Level are continuing.
■
Significant capital expenditure has been invested in these mining levels to improve and optimise infrastructure and to ensure sustainable production of approximately 65,000oz annually over the mine’s life of c 11 years.
■
Although delayed, equipping of the existing 17 Level underground ventilation shaft to hoist at a rate of up to 40,000tpm is now imminent, improving efficiencies and circumventing the ageing conveyor belt system.
■
The newly commissioned 24 Level refrigeration plant will provide chilled water to a bulk air cooler on 24 Level, with a nominal cooling capacity of 3.5MW, to create improved working conditions on both 24 and 25 Levels.
■
Development of the existing 24 Level footwall infrastructure to access 25 Level, through an on-reef decline layout, is planned to commence in FY25 (NB access to 25 Level mining areas is expected to be completed in FY26).
BTRP life of mine extension and Royal Sheba
Following an internal process to consider feedstock sources for the BTRP, final drilling and metallurgical test work results were recently retrieved from Bramber’s dormant tailings storage facility (TSF), which will increase the life of the BTRP from two to seven years.
■
The BTRP has deposited its residues on the Bramber dormant footprint since inception (in 2013). In November 2017, a regrind mill was added to the slurry receiving section and, in CY23, phase 2 of the Aachen Assisted Leach (AAL) reactor was commissioned.
■
The Bramber dormant TSF contains 6Mt of previously treated BTRP and Fairview Mine residue at an average grade of 1.0g/t.
■
The impact on expected gold recoveries following the addition of the regrind mill and AAL was used to test the Bramber dormant mine residue. To date:
•
Metallurgical test work indicates that recoveries of 18–27% of the remaining gold content in this resource are achievable.
•
Utilising the 90th percentile of the recoveries achieved (25% recovery) in the financial model, Pan African estimated that this source of tailings material will extend the BTRP’s tailings feed life from two to seven years, producing approximately 11,000oz per year at an average real AISC of US$1,485/oz.
In the meantime, Pan African will focus on developing the Sheba Fault decline to access high grade mineral reserves to supplement Barberton Mines’ production in the medium term and longer term. Preliminary optimisation work at Sheba and Western Cross indicates:
■
An eight-year lifespan at Royal Sheba, with production of around 235,000oz of gold at an average mining grade of 3g/t over the life of mine, with the potential for further extensions as the orebody remains open at depth. First stoped ore is planned at a rate of 5,000t per month, ramping up to 10,000t, 30,000t and 45,000t per month, every 12 months thereafter in line with a set lateral and vertical development schedule.
■
The Western Cross orebody at the Sheba Mine is a lower-grade (3–4g/t) 10m wide free-milling orebody that is currently accessed via the South Wall Adit and forms part of the mine’s production profile. The orebody is amenable to bulk mining, similar to that planned at Royal Sheba. Drilling in FY25 is planned to update the geological model, confirm available mineral resource blocks and update the existing feasibility study.
Egoli
The Egoli project at Evander Mines’ 7 Shaft is a standalone underground operation that will utilise existing mining and metallurgical infrastructure, including 7 Shaft’s hoisting systems and processing facilities at Kinross’s metallurgical plant.
■
First phase development, involving the dewatering of the project’s 7 Shaft number 3 Decline to below 20 Level has now been completed and permanent pumping infrastructure installed.
■
Egoli will be accessed directly from 7 Shaft’s 15 Level using existing declines to 19 Level, where a new on-reef decline will be established to access the orebody to 23 Level.
■
All the required permits for the Egoli project, including Evander Mines’ mining right (valid until 2038) have been approved.
■
Leveraging existing infrastructure, Egoli can increase Evander Mines’ production profile for a relatively low capital cost and within a relatively short time frame.
■
The second phase of Egoli’s development will involve establishing a drilling platform on 19 Level in Q125, from which long-inclined boreholes will be drilled to accurately define short-term grade variability and geological structures.
Group
In the light of these developments (including PAF’s unchanged guidance for FY25), we continue to forecast that group production at PAF will reach c 250koz per year in 2026 and push normalised headline EPS (HEPS) to beyond 7.00c per share (see Exhibit 10).
|
Exhibit 6: Estimated Pan African group gold production profile, FY18–29e |
|
|
Source: Edison Investment Research, Pan African Resources |
Dividend and dividend policy
After three years of holding its dividend at ZAR0.18/share, PAF declared a dividend of ZAR0.22/share (c 1.2584 US cents or 0.9476 pence per share at prevailing forex rates) for FY24 for approval at its forthcoming annual general meeting (AGM) on 21 November. In addition, the company explicitly set out a dividend policy targeting a payout ratio of 40–50% of net cash generated from operating activities, after providing for the cash flow impact of capital expenditure (reduced by externally funded capital), contractual debt repayments and the cash flow impact of one-off items (discretionary rand cash flow). In proposing a dividend, the board will also take account of the company’s financial position, prospects, satisfactory solvency and liquidity assessments and other factors deemed by the board to be relevant at the time.
FY24’s dividend of ZAR0.22/share followed three years of a static dividend at ZAR0.18/share, during which time the company was either in the midst of, or anticipating, a period of material capital investment. Within this context, FY25 should be the last year in the foreseeable future of material capital outlay for PAF. Where before we had assumed that Pan African would pay out a flat dividend in FY25, followed by its maximum potential dividend from FY26 (for valuation purposes), in the light of the company’s dividend policy statement, we have now assumed that it will declare a dividend according to its restated policy in FY25–28 followed by its maximum potential dividend from FY29. In FY25 we believe that this will continue to be relatively conservative as capex remains elevated at the same time that PAF will be required to make debt capital repayments. For FY26 and beyond, however, we believe that the possibility exists for materially increased dividend payouts as production increases, operating costs flatten and capital expenditure falls away.
Updated (absolute) valuation
In deriving our longer-term estimates for PAF over the life of its operations, we have made a number of changes, the most material of which are summarised below:
■
We have adjusted the production profiles of Evander 25 Level, the BTRP, Elikhulu and Mogale to reflect PAF’s guidance for FY25 and beyond (see PAF’s results presentation).
■
We have updated our assumed profits and losses from the hedge relating to its synthetic forward sale of gold as part of the financing package for Mintails/Mogale. We have also added to this profits and losses from its separate zero-cost collars, which form part of the company’s discretionary hedging policy. As in FY24, we include all these in ‘other income/expenses’ on the group’s income statement.
■
We have brought capex into line with company guidance of ZAR2,273m for FY25.
■
We have increased our estimate of long-term unit costs at Elikhulu by 12.1% from ZAR60.29/t (in real FY24 terms) to ZAR67.58/t in real FY25 terms over the life of its operations (cf a figure of ZAR67.00/t in FY24).
|
Exhibit 7: Elikhulu cash cost per tonne (ZAR/t, H119–H224) |
|
|
Source: Pan African Resources |
■
We have increased our forecast of working costs at Barberton by 12.6% from ZAR5,281/t (real FY24 terms) to ZAR5,947/t in real FY25 terms (cf a figure of ZAR5,493/t in FY24).
|
Exhibit 8: Barberton cash cost per tonne (ZAR/t, FY09–24) |
|
|
Source: Pan African Resources |
In addition to changes to our immediate operational assumptions, we have adjusted our long-term foreign exchange rates (in real terms), to reflect the recent ‘above trend’ strength of the rand (and to a lesser extent sterling) against the US dollar:
■
From ZAR23.5894/£ at the time of our last note to ZAR23.2165/£ (-1.6%), being that prevailing at the time of writing.
■
From ZAR18.3996/US$ to ZAR17.4830/US$ (-5.0%).
■
From US$1.2833/£ to US$1.3279/£ (+3.5%).
|
Exhibit 9: South African rand (ZAR) per US dollar (H113–H225e) |
|
|
Source: Edison Investment Research, Pan African Resources |
In the aftermath of these changes, our absolute valuation of PAF (based on its existing four producing assets plus the 25 and 26 Level project and Mogale) has reverted to its pre-May 2024 level of 40.93c (cf 49.39c in July – see Exhibit 12), which is based on the present value of the estimated potential dividend stream payable to shareholders over the life of its mining operations (applying a 10% discount rate to US dollar dividends).
|
Exhibit 10: PAF estimated life of operations’ diluted EPS and (maximum potential*) DPS |
|
|
Source: Pan African Resources, Edison Investment Research. Note: *From FY29. Excludes discretionary exploration investment. |
This may be compared with the equivalent graph from July 2024, as follows:
|
Exhibit 11: Pan African estimated life of operations’ EPS and (maximum potential*) DPS (at July 2024) |
|
|
Source: Pan African Resources, Edison Investment Research. Note: Excludes discretionary exploration investment. *From FY26. |
Readers’ attention is drawn to the flattened profile of dividends assumed in FY25–28 in our updated valuation relative to our July 2024 valuation, which have been calculated with due regard to PAF’s dividend policy, but which has resulted in a reduction in valuation of 3.02c/share as a result of the deferral of higher dividends.
Including its other growth projects and assets, our updated total valuation of PAF as a whole is provided in Exhibit 12, below.
Exhibit 12: PAF group absolute valuation summary
Project |
Current valuation |
July 2024 valuation |
February 2024 valuation (US$/share) |
Existing producing assets* |
39.67 |
48.41 |
41.15 |
Cum-FY24 dividend |
1.26 |
0.98 |
- |
Royal Sheba** |
1.30 |
0.98 |
0.63 |
Other** |
2.24 |
1.70 |
1.14 |
Sub-total |
44.47 |
52.07 |
42.92 |
EGM underground resource |
0.22–5.24 |
0.22–5.24 |
0.22–5.24 |
Sub-total |
44.69-49.71 |
52.29–57.31 |
43.14–48.16 |
Egoli |
16.59 |
16.98 |
17.09 |
Soweto cluster |
1.95 |
1.49 |
1.93 |
Total |
63.23-68.25 |
70.76–75.78 |
62.16–67.18 |
Source: Edison Investment Research. Note: *Including 24 Level and 25 & 26 Level and Mogale projects. **Resource based valuations. Numbers may not add up owing to rounding.
An analysis of the change in valuation according to each separate adjustment to our assumptions is provided in the graph below:
|
Exhibit 13: Pan African Resources valuation change by item (September 2024 cf July 2024) |
|
|
Source: Edison Investment Research |
Historical relative and current peer group valuation
Historical relative valuation
Exhibit 14 below depicts PAF’s average share price in each of the financial years from FY10 to FY24 and compares this with HEPS in the same year. For FY25 and FY26, the current share price (33.65p) is compared with our forecast normalised HEPS for those years. As is apparent from the chart, PAF’s price to normalised HEPS ratios of 6.1x and 6.7x for FY25 and FY26, respectively, remain close to the bottom of its recent historical range of 4.1–14.8x for the period FY10–24 and consistent with its range of 4.1–7.0x for the period FY19–24:
|
Exhibit 14: PAF historical price to normalised HEPS** ratio, FY10–26e |
|
|
Source: Edison Investment Research. Note: *Completed historical years calculated with respect to average share price within the year shown and normalised HEPS; zero normalisation assumed before 2016. **HEPS shown in pence prior to 2018 and US cents thereafter. |
If PAF’s average year one price to normalised EPS ratio of 8.2x for the period FY10–24 is applied to our normalised earnings forecasts, it implies a share price for PAF of 44.70p in FY25 followed by one of 41.17p in FY26. Stated alternatively, PAF’s current share price of 33.65p, at prevailing foreign exchange rates, appears to be discounting FY25 and/or FY26 normalised HEPS of 5.48c per share (cf our forecasts of 7.28c and 6.71c, respectively).
Relative peer group valuation
In the meantime, it may be seen that PAF remains cheaper than its London- and South African-listed gold mining peers on 80% of comparable common valuation measures (29 out of 36 individual measures in the table below) regardless of whether Edison or consensus forecasts are used.
Exhibit 15: Comparative valuation of PAF with South African and London peers
Company |
EV/EBITDA (x) |
P/E (x) |
Yield (%) |
|||
Year 1 |
Year 2 |
Year 1 |
Year 2 |
Year 1 |
Year 2 |
|
AngloGold Ashanti |
5.0 |
4.6 |
11.1 |
9.3 |
2.1 |
1.9 |
Gold Fields |
5.5 |
4.1 |
12.4 |
8.0 |
3.2 |
4.7 |
Sibanye Stillwater |
3.8 |
3.1 |
10.7 |
5.5 |
5.2 |
6.0 |
Harmony |
4.4 |
4.3 |
8.1 |
8.2 |
1.9 |
2.1 |
Centamin |
4.0 |
3.4 |
10.2 |
11.0 |
2.5 |
3.9 |
Endeavour Mining (consensus) |
5.1 |
4.0 |
14.4 |
9.4 |
3.3 |
4.0 |
Average (excluding PAF) |
4.6 |
3.9 |
11.1 |
8.6 |
3.0 |
3.8 |
PAF (Edison) |
4.1 |
4.2 |
6.1 |
6.7 |
3.3 |
11.6 |
PAF (consensus) |
4.1 |
3.5 |
6.7 |
5.5 |
3.5 |
5.9 |
Source: Edison Investment Research, LSEG Data & Analytics. Note: Consensus and peers priced at 24 September 2024.
Alternatively, applying PAF’s peer average year one P/E ratio of 11.1x to our normalised HEPS forecast of 7.28c per share for FY25 implies a share price for the company of 61.03p at prevailing foreign exchange rates. Applying its peer average year two P/E ratio of 8.6x to our normalised HEPS forecast of 6.71c per share for FY26 implies a share price of 43.33p.
Financials
Pan African reported net debt of US$104.4m on its balance sheet as at end-June 2024 (cf US$61.7m as at end-December 2023 and US$22.1m as at end-June 2023), which equated to a gearing ratio (net debt/equity) of 28.6% (cf 18.8% at end-December 2023 and 7.5% at end-June 2023) and a leverage ratio (net debt/[net debt+equity]) of just 22.2% (cf 15.8% at end-December 2023 and 7.0% at end-June 2023), after cash flow from operating activities of US$109.1m before dividends (cf US$45.5m in H124, US$88.5m in H223 and US$31.6m in H123). Capex guidance for FY25 is ZAR2.27bn (c US$130.0m at prevailing foreign exchange rates). Beyond that, we forecast that PAF will continue to generate cash from operations comfortably above the US$100m pa level (and potentially close to US$200m pa) into the foreseeable future, such that we calculate that net debt will peak in CY24 (in reality at end-December 2024), before being eliminated in FY26, by which time we assume that capex will once again have returned to near-sustaining levels.
|
Exhibit 16: Pan African current estimated net debt* profile forecast, FY17–26e (annually) |
|
|
Source: Edison Investment Research, Pan African Resources. Note: *Excluding ‘other’ (see Exhibits 17 and 19). |
Note that, for the purposes of these forecasts, we have assumed that FY24’s dividend will be paid in FY25 and that our newly increased FY25 dividend estimate will be paid in FY26.
Including all other components, total net debt as at end-June was US$106.4m (cf US$64.3m at end-December, US$22.0m at end-June and US$53.7m at end-December 2022), as shown below:
Exhibit 17: Pan African components of total net debt (US$m)
US$m |
FY20 |
H121 |
FY21 |
H122 |
FY22 |
H123 |
FY23 |
H124 |
FY24 |
Long-term debt to financial institutions |
28.0 |
48.2 |
|||||||
Short-term debt to financial institutions |
30.7 |
0.3 |
|||||||
Total debt to financial institutions |
89.2 |
87.8 |
58.7 |
48.5 |
26.2 |
75.0 |
53.4 |
89.8 |
127.8 |
Cash |
33.5 |
28.0 |
35.1 |
35.2 |
27.0 |
33.9 |
34.8 |
31.3 |
26.3 |
Net debt to financial institutions |
55.7 |
59.8 |
23.6 |
13.3 |
(0.8) |
41.1 |
18.6 |
58.5 |
101.5 |
RedInk Rentals loan facility |
9.9 |
8.9 |
8.4 |
7.5 |
- |
- |
- |
||
Other* |
6.6 |
0.3 |
0.2 |
1.7 |
1.7 |
1.3 |
0.3 |
1.6 |
1.3 |
Net senior debt |
62.3 |
60.1 |
33.7 |
23.9 |
9.3 |
49.9 |
18.9 |
60.1 |
102.8 |
Lease liabilities |
14.1 |
5.0 |
5.3 |
4.5 |
4.4 |
4.3 |
3.5 |
3.3 |
3.0 |
Other |
0.0 |
0.0 |
0.0 |
(0.2) |
(0.7) |
(0.5) |
(0.4) |
0.9 |
0.7 |
Total net debt |
76.4 |
65.2 |
39.0 |
28.2 |
13.0 |
53.7 |
22.0 |
64.3 |
106.4 |
Change |
N/A |
(11.2) |
(26.2) |
(10.8) |
(15.2) |
(40.7) |
(31.7) |
42.3 |
42.1 |
Source: Pan African Resources. Note: Totals may not add up owing to rounding. *Including restricted cash.
The US$2.0m difference between net debt of US$106.4 and net debt of US$104.4m as per Exhibit 19 is accounted for by the US$2.0m of ‘other’ items included in Exhibit 17.
In the meantime, the group remains very comfortably within its revolving credit facility debt covenants:
Exhibit 18: Pan African group debt covenants
Measurement |
Constraint |
H119 |
FY19 |
H120 |
FY20 |
H121 |
FY21 |
H122 |
FY22 |
H123 |
FY23 |
H124 |
FY24 |
Net debt:equity |
Must be less than 1:1 |
0.85 |
0.71 |
0.6 |
0.4 |
0.3 |
0.1 |
0.1 |
0.04 |
0.2 |
0.07 |
0.2 |
0.29 |
Net debt:adjusted EBITDA |
Must be less than 2:1 |
3.24 |
2.2 |
1.6 |
0.7 |
0.5 |
0.3 |
0.2 |
0.1 |
0.5 |
0.2 |
0.5 |
0.8 |
Interest cover ratio |
Must be greater than 4x |
3.64 |
4.1 |
5.8 |
10.1 |
17.7 |
23.0 |
29.0 |
34.1 |
26.9 |
18.4 |
16.7 |
12.2 |
Debt service cover ratio |
Must be greater than 1:3 |
2.85 |
1.4 |
3.0 |
3.4 |
3.3 |
3.0 |
3.0 |
7.3 |
8.5 |
7.5 |
4.6 |
3.8 |
Source: Pan African Resources
Exhibit 19: Financial summary
US$'000s |
2022 |
2023 |
2024 |
2025e |
2026e |
||
Year end 30 June |
IFRS |
IFRS |
IFRS |
IFRS |
IFRS |
||
PROFIT & LOSS |
|||||||
Revenue |
|
|
376,371 |
321,606 |
373,796 |
459,298 |
477,347 |
Cost of sales |
(226,445) |
(198,790) |
(221,183) |
(223,459) |
(246,390) |
||
Gross profit |
149,926 |
122,816 |
152,613 |
235,840 |
230,958 |
||
EBITDA |
|
|
147,830 |
121,853 |
150,926 |
231,257 |
227,384 |
Operating profit (before amort. and excepts.) |
|
|
121,402 |
101,454 |
129,682 |
192,042 |
178,152 |
Intangible amortisation |
0 |
0 |
0 |
0 |
0 |
||
Exceptionals |
(10,295) |
(7,347) |
(10,375) |
(16,214) |
(1,662) |
||
Other |
0 |
0 |
0 |
0 |
0 |
||
Operating profit |
111,107 |
94,107 |
119,307 |
175,828 |
176,489 |
||
Net interest |
(4,231) |
(8,553) |
(9,900) |
(9,396) |
(8,785) |
||
Profit Before Tax (norm) |
|
|
117,171 |
92,901 |
119,782 |
182,645 |
169,367 |
Profit before tax (FRS 3) |
|
|
106,876 |
85,554 |
109,407 |
166,432 |
167,705 |
Tax |
(31,924) |
(24,817) |
(30,581) |
(43,079) |
(40,823) |
||
Profit after tax (norm) |
85,247 |
68,084 |
89,201 |
139,566 |
128,544 |
||
Profit after tax (FRS 3) |
74,952 |
60,737 |
78,826 |
123,353 |
126,882 |
||
Average Number of Shares Outstanding (m) |
1,926.1 |
1,916.5 |
1,916.5 |
1,916.5 |
1,916.5 |
||
EPS - normalised (c) |
|
|
4.44 |
3.54 |
4.68 |
7.28 |
6.71 |
EPS - FRS 3 (c) |
|
|
3.90 |
3.19 |
4.14 |
6.44 |
6.62 |
Dividend per share (c) |
1.04 |
0.95 |
1.26 |
1.49 |
5.16 |
||
Gross margin (%) |
39.8 |
38.2 |
40.8 |
51.3 |
48.4 |
||
EBITDA margin (%) |
39.3 |
37.9 |
40.4 |
50.4 |
47.6 |
||
Operating margin (before GW and except.) (%) |
32.3 |
31.5 |
34.7 |
41.8 |
37.3 |
||
BALANCE SHEET |
|||||||
Fixed assets |
|
|
401,139 |
439,676 |
625,678 |
712,692 |
687,665 |
Intangible assets |
44,210 |
44,429 |
42,454 |
44,747 |
47,053 |
||
Tangible assets |
355,802 |
395,247 |
579,851 |
664,571 |
637,239 |
||
Investments |
1,127 |
0 |
3,373 |
3,373 |
3,373 |
||
Current assets |
|
|
55,953 |
61,263 |
57,938 |
48,541 |
66,758 |
Stocks |
9,977 |
9,567 |
16,431 |
15,321 |
15,921 |
||
Debtors |
17,546 |
15,182 |
15,175 |
32,740 |
34,024 |
||
Cash |
26,993 |
34,771 |
26,332 |
480 |
16,813 |
||
Current liabilities |
|
|
(58,989) |
(77,386) |
(84,864) |
(99,207) |
(192,485) |
Creditors |
(57,117) |
(65,884) |
(79,344) |
(93,687) |
(186,965) |
||
Short-term borrowings |
(1,872) |
(11,502) |
(5,520) |
(5,520) |
(5,520) |
||
Long-term liabilities |
|
|
(103,494) |
(128,957) |
(237,104) |
(205,527) |
(77,480) |
Long-term borrowings |
(37,088) |
(45,334) |
(125,214) |
(92,566) |
36,242 |
||
Other long-term liabilities |
(66,406) |
(83,623) |
(111,890) |
(112,961) |
(113,722) |
||
Net assets |
|
|
294,609 |
294,596 |
361,648 |
456,499 |
484,457 |
CASH FLOW |
|||||||
Operating Cash Flow |
|
|
142,879 |
132,941 |
134,310 |
169,635 |
228,487 |
Net Interest |
(2,794) |
(5,121) |
(9,731) |
(9,396) |
(8,785) |
||
Tax |
(8,520) |
(7,722) |
(15,476) |
(16,781) |
(21,855) |
||
Capex |
(81,951) |
(109,952) |
(169,521) |
(126,229) |
(24,205) |
||
Acquisitions/disposals |
563 |
(2,779) |
141 |
0 |
0 |
||
Financing |
(3,222) |
0 |
0 |
0 |
0 |
||
Dividends |
(21,559) |
(19,975) |
(18,302) |
(18,302) |
(28,501) |
||
Net cash flow |
25,396 |
(12,608) |
(78,579) |
(1,074) |
145,141 |
||
Opening net debt/(cash) |
|
|
23,553 |
11,967 |
22,065 |
104,402 |
97,606 |
Exchange rate movements |
(4,401) |
(4,481) |
1,160 |
0 |
0 |
||
Other |
(9,409) |
6,991 |
(4,918) |
7,870 |
0 |
||
Closing net debt/(cash) |
|
|
11,967 |
22,065 |
104,402 |
97,606 |
(47,535) |
Source: Company sources, Edison Investment Research. Note: FY24 on ‘as reported’ basis cf ‘adjusted’ basis (see Exhibit 4). FY23 ‘as reported’ and not restated as per FY24 results (NB restatement deemed immaterial by Edison).
|
|
Research: Investment Companies
Greencoat Renewables’ (GRP’s) large and diversified pan-European portfolio of renewable energy assets generated net cash of €113.6m in H124 (H123: €125.5m). This equated to gross dividend cover of 3x at end-H124 and a six-month return of 8.6% on its December 2023 net asset value (NAV). NAV per share remained flat at 112.1c, due to less impactful power price movements in the period and strong cash generation offsetting depreciation and dividend payments. GRP’s weighted average cost of debt reduced from 3.3% to 3.1%, due to terming out of a more expensive RCF debt and refinancing a new €150m five-year debt facility in February 2024. The company’s total aggregate debt stood at €1.3bn at end-H124, being 98% fixed or effectively fixed through interest rate swaps. GRP currently trades at a 16% discount to NAV with a 7.2% dividend yield.