Last close As at 05/08/2026
CAD172.48
▲ 10.06 (6.19%)
Market capitalisation
CAD78,334m
Research: Metals & Mining
Wheaton’s Q223 results exceeded our expectations. Production of gold equivalent ounces (GEOs) was 4.6% higher than our prior forecasts, while sales of GEOs were 6.9% higher, driving a positive variance in revenue of 6.6%, or US$16.4m. This was partially offset by costs but nevertheless resulted in a US$7.8m (or 5.4%) positive variance in earnings from operations that, to all intents and purposes, dropped through to the bottom line.
Wheaton Precious Metals |
Peerless |
Q223 results |
Metals and mining |
15 August 2023 |
Share price performance
Business description
Next events
Analyst
Wheaton Precious Metals is a research client of Edison Investment Research Limited |
|||||||||||||||||||||||||||||||||||||||||||||||||||
Wheaton’s Q223 results exceeded our expectations. Production of gold equivalent ounces (GEOs) was 4.6% higher than our prior forecasts, while sales of GEOs were 6.9% higher, driving a positive variance in revenue of 6.6%, or US$16.4m. This was partially offset by costs but nevertheless resulted in a US$7.8m (or 5.4%) positive variance in earnings from operations that, to all intents and purposes, dropped through to the bottom line.
Year end |
Revenue |
PBT* |
EPS* |
DPS |
P/E |
Yield |
12/21 |
1,201.7 |
592.1 |
132 |
57 |
33.4 |
1.3 |
12/22 |
1,065.1 |
497.7 |
112 |
60 |
39.3 |
1.4 |
12/23e |
1,030.4 |
502.5 |
118 |
60 |
37.4 |
1.4 |
12/24e |
1,424.9 |
668.7 |
147 |
64 |
29.9 |
1.5 |
Note: *PBT and EPS are normalised, excluding amortisation of acquired intangibles and exceptional items.
Salobo III ramp-up still in its early stages
Wheaton’s outperformance in Q223 could largely be attributed to an excellent production result at Salobo, where the ramp-up of Salobo III is proceeding ahead of schedule (it contributed 30.9% of total Salobo copper production in Q223, cf an expected 33.3% pro-rata to throughput at full capacity). Had it not been for a natural lag between copper and gold production during the ramp-up process, we estimate that Salobo III would otherwise have added an additional 4,790oz to WPM’s production in Q2.
Penasquito assumed offline until the end of August
Notwithstanding the current stoppage at Penasquito (which we expect to be concluded by the end of the month), we are still expecting H223 production to exceed H123 production in the ratio 53:47, driven by increases in output at Salobo and Constancia, in particular. In deference to the recent weakness in metals prices, we have shaved our earnings forecasts for Q3 and Q423. However, the effect on our full year forecast is an immaterial -4.8%.
Valuation: Heading towards C$70/share
Using a capital asset pricing model (CAPM)-type method, whereby we discount cash flows at a nominal 9% per year, our ‘terminal’ valuation of WPM in FY26 is little changed at US$54.88 (C$73.76) per share, assuming zero subsequent longterm growth in real cash flows. Alternatively, assuming no purchases of additional streams (which we think unlikely), we calculate a value per share for WPM of US$56.71 or C$76.23 or £44.72 in FY26, based on a 30.4x historical multiple of contemporary earnings. In the meantime, WPM’s shares are trading on near-term financial ratios that are lower than those of its peers on at least 63% of common valuation measures if Edison forecasts are used or 50% if consensus forecasts are used. Stated alternatively, if WPM were to trade at the average multiples of its peers, we calculate that its share price should be US$50.40, or C$67.75 currently.
Q223 results
In general, in the second quarter, Wheaton’s production and sales of gold, palladium and cobalt were all higher than our prior expectations and, although sales of silver were also higher, production of silver was slightly lower. Overall, production of GEOs was 4.6% higher than our prior forecasts for the quarter, while sales of GEOs were 6.9% higher, driving a positive variance in revenue of 6.6%, or US$16.4m. This was partially offset by costs of sales that were 8.2%, or US$8.6m higher, which drove a 5.4%, or US$7.8m, positive variance in earnings from operations that, to all intents and purposes, dropped through to the bottom line. An exceptional charge of US$15m (Edison estimate) that we thought might arise as a consequence of the suspension of activities at the Minto mine during the quarter ultimately did not do so. A complete analysis of WPM’s underlying financial and operating results relative to both Q123 and Edison’s prior expectations is provided in the exhibit below:
Exhibit 1: WPM Q223 results*
US$000s |
Q422 |
Q123 |
Q223e |
Q223e (inc excepts) |
Q223 |
Q223 (inc excepts) |
Change (%) |
Variance (%) |
Variance (units) |
Silver production (koz) |
5,352 |
4,927 |
4,635 |
4,635 |
4,417 |
4,417 |
-10.4 |
-4.7 |
-218 |
Gold production (oz) |
70,099 |
73,037 |
76,449 |
76,449 |
85,083 |
85,083 |
16.5 |
11.3 |
8,634 |
Palladium production (oz) |
3,869 |
3,705 |
3,514 |
3,514 |
3,880 |
3,880 |
4.7 |
10.4 |
366 |
Cobalt production (klb) |
128 |
124 |
124 |
124 |
152 |
152 |
22.6 |
22.6 |
28 |
Silver sales (koz) |
4,935 |
3,749 |
4,185 |
4,185 |
4,437 |
4,437 |
18.4 |
6.0 |
252 |
Gold sales (oz) |
68,996 |
62,605 |
71,306 |
71,306 |
75,294 |
75,294 |
20.3 |
5.6 |
3,988 |
Palladium sales (oz) |
3,396 |
2,946 |
3,161 |
3,161 |
3,392 |
3,392 |
15.1 |
7.3 |
231 |
Cobalt sales (klb) |
187 |
323 |
124 |
124 |
265 |
265 |
-18.0 |
113.7 |
141 |
Average realised Ag price (US$/oz) |
21.52 |
22.85 |
24.19 |
24.19 |
24.13 |
24.13 |
5.6 |
-0.2 |
-0.06 |
Average realised Au price (US$/oz) |
1,725 |
1,904 |
1,976 |
1,976 |
1,986 |
1,986 |
4.3 |
0.5 |
10 |
Average realised Pd price (US$/oz) |
1,939 |
1,607 |
1,445 |
1,445 |
1,438 |
1,438 |
-10.5 |
-0.5 |
-7 |
Average realised Co price (US$/lb) |
22.62 |
15.04 |
14.79 |
14.79 |
13.23 |
13.23 |
-12.0 |
-10.5 |
-1.56 |
Average Ag cash cost (US$/oz) |
5.00 |
5.07 |
5.21 |
5.21 |
5.01 |
5.01 |
-1.2 |
-3.8 |
-0.20 |
Average Au cash cost (US$/oz) |
475 |
496 |
456 |
456 |
461 |
461 |
-7.1 |
1.1 |
5 |
Average Pd cash cost (US$/oz) |
357 |
294 |
260 |
260 |
261 |
261 |
-11.2 |
0.4 |
1 |
Average Co cash cost (US$/lb) |
***16.52 |
***3.30 |
2.66 |
2.66 |
3.20 |
3.20 |
-3.0 |
20.3 |
0.54 |
Sales |
236,051 |
214,465 |
248,534 |
248,534 |
264,972 |
264,972 |
23.6 |
6.6 |
16,438 |
Cost of sales |
|||||||||
Cost of sales, excluding depletion |
61,730 |
51,964 |
55,487 |
55,487 |
58,642 |
58,642 |
12.9 |
5.7 |
3,155 |
Depletion |
53,140 |
45,000 |
49,026 |
49,026 |
54,474 |
54,474 |
21.1 |
11.1 |
5,448 |
Total cost of sales |
114,870 |
96,964 |
104,512 |
104,512 |
113,116 |
113,116 |
16.7 |
8.2 |
8,604 |
Earnings from operations |
121,181 |
117,501 |
144,022 |
144,022 |
151,856 |
151,856 |
29.2 |
5.4 |
7,834 |
Expenses and other income |
|||||||||
– General and administrative** |
19,773 |
18,874 |
15,280 |
15,280 |
16,640 |
16,640 |
-11.8 |
8.9 |
1,360 |
– Foreign exchange (gain)/loss |
|||||||||
– Interest paid/(received) |
1,377 |
1,378 |
1,454 |
1,454 |
1,352 |
1,352 |
-1.9 |
-7.0 |
-102 |
– Other (income)/expense |
(3,935) |
(7,387) |
(7,968) |
2,062 |
(8,811) |
(13,719) |
19.3 |
10.6 |
-843 |
Total expenses and other income |
17,215 |
12,865 |
8,766 |
18,796 |
9,182 |
4,273 |
-28.6 |
4.7 |
416 |
Earnings before income taxes |
103,966 |
104,636 |
135,256 |
125,226 |
142,675 |
147,583 |
36.4 |
5.5 |
7,419 |
Income tax expense/(recovery) |
222 |
205 |
250 |
250 |
91 |
6,135 |
-55.6 |
-63.6 |
-159 |
Marginal tax rate (%) |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
4.2 |
-50.0 |
-50.0 |
-0.1 |
Net earnings |
103,744 |
104,431 |
135,006 |
124,976 |
142,584 |
141,448 |
36.5 |
5.6 |
7,578 |
Average no. shares in issue (000s) |
452,070 |
452,370 |
452,838 |
452,838 |
452,892 |
452,892 |
0.1 |
0.0 |
54 |
Basic EPS (US$) |
0.229 |
0.231 |
0.298 |
0.276 |
0.315 |
0.312 |
36.4 |
5.7 |
0.017 |
Diluted EPS (US$) |
0.229 |
0.230 |
0.297 |
0.275 |
0.314 |
0.312 |
36.5 |
5.7 |
0.017 |
DPS (US$) |
0.15 |
0.15 |
0.15 |
0.15 |
0.15 |
0.15 |
0.0 |
0.0 |
0.00 |
Source: WPM accounts, Edison Investment Research. Note: Change is Q223 cf Q123 (excluding exceptional items). Variance is actual cf forecast excluding exceptional items. *Excluding impairments, impairment reversals and exceptional items (except where indicated). **Forecasts now include stock-based compensation costs. ***Cobalt inventory is held on WPM’s balance sheet at the lower of cost and net realisable value; cash cost per pound of cobalt sold during Q422 included an inventory impairment charge of US$1.6m, which resulted in an increase in cash costs of US$8.71/lb; cash cost per pound of cobalt sold during Q123 was net of the previously recorded inventory write-down of US$1.0m, which resulted in a decrease in cash costs of US$3.18/lb; cash cost per pound of cobalt sold during Q223 was net of a previously recorded inventory write-down of US$0.5m, which resulted in a decrease in cash costs of US$1.81/lb. Totals may not add up owing to rounding.
At the level of the individual mines, Penasquito, Cozamin, Salobo, San Dimas, Voisey’s Bay and Stillwater all unequivocally outperformed our prior (sometimes quite conservative) expectations, while Zinkgruvan and Aljustrel slightly underperformed.
Compared with the prior year period, Antamina, Constancia and Voisey’s Bay all experienced lower grades. At the same time, output and sales at Salobo were notable for having been driven by higher throughput and grades. According to Vale, production in the second quarter was driven by a better-than-expected ramp up of Salobo III partially offset by planned maintenance activities and additional work on the crushers at Salobo I and II. Vale reports that planned maintenance activities will continue in the second half of 2023, and that the ramp up of Salobo III is expected to be fully completed in 2024. Contrary to our prior expectations, most of the gold production associated with Salobo III (we estimate 75% cf our prior expectation of 25%) was recovered to Wheaton’s account during the quarter. Had all of the gold anticipated to be produced, given Salobo’s level of copper production, been produced, we estimate that it would have added a further 4,790oz to WPM’s production in Q223, as shown in the graph below:
|
Exhibit 2: Salobo copper production versus gold production attributable to WPM, Q316–Q223 |
|
|
Source: Edison Investment Research (underlying data: Wheaton Precious Metals and Vale) |
Entering Q323:
■
Operations at Penasquito (17.5% of sales in Q223) remain suspended. Newmont announced a suspension of operations at Penasquito on 8 June. In its Q223 results call, Newmont stated that it believed its original agreement with the unions at Penasquito was firm and equitable. As such, it is resolved to be firm in its adherence to the terms of that agreement already in place and not to allow its renegotiation. In the meantime, it confirmed that the unions are not making payments to their members and that Newmont will also not be making back payments. As a result, it hopes that the unions will eventually encourage their members to return to work. In the absence of any immediate, official progress in resolving the dispute between Newmont and the unions at Penasquito, we have assumed that production and sales will continue to be affected by the suspension for two of the three months of Q3 until the end of August.
■
Operations at Minto (estimated 0.6% of sales in Q223) similarly remain suspended. Minto announced the cessation of operations on 13 May after failing to raise funds, after which its full complement of directors resigned on 16 May. As a result, we have removed all production and sales from Minto, attributable to Wheaton, from our financial models indefinitely.
■
Production at the Stillwater mine (3.5% of sales in Q223) has recommenced after an incident (during scheduled non-routine maintenance) caused structural damage to the shaft headgear, winder house and winder rope, which resulted in production from the Stillwater West mine below the 50 level being suspended for approximately five weeks from 13 March. However, it recommenced on 16 April, and, as noted previously, the mine outperformed our prior forecasts for the quarter for both production and sales in Q223.
■
Full mining activities have resumed in the Pampacancha pit at Constancia (13.4% of sales in Q223), with the mining of higher-grade ore now underway. After a period of higher stripping in Q223 (that ended in June) we are therefore forecasting that gold production attributable to Wheaton from Constancia, in particular, will increase by more than 75% in Q3 and Q423 (or c 5,594oz per quarter) relative to Q223.
■
Voisey’s Bay (1.3% of sales in Q223) is continuing to mine lower-grade material during its ongoing transition between the depletion of the Ovoid open-pit mine and ramp-up to full production of the Voisey’s Bay underground project. Production in the second quarter was also affected by an annual maintenance schedule at the Long Harbour refinery (from May to July) that was longer than in 2022. Vale reports that physical completion of the Voisey’s Bay underground mine extension was 85% at the end of Q223 (cf 83% at end-Q123), with Reid Brook’s bulk material handling system expected to be delivered in Q323 and lateral development advancing on the Eastern Deeps. Vale achieved its first ore production from the Reid Brook deposit, the first of two underground mines to be developed at Voisey’s Bay, in Q221. Eastern Deeps, the second deposit, has now also started to extract development ore from the mine and is scheduled to start its main production ramp-up in the second half of the year.
Ounces produced but not yet delivered
At 11.5%, the degree of under-sale of gold in Q223, relative to production, was slightly greater than the prior historical average of 6.7% (from Q112 until Q123). By contrast, the 0.5% over-sale of silver relative to production was materially better than its prior historical average of a 12.1% under-sale and contributed to a notable run down in silver ounces produced but not sold (see below).
|
Exhibit 3: Over/(under) sale of silver and gold as a percentage of production, Q112–Q223 |
|
|
Source: Edison Investment Research, WPM. Note: As reported. |
As a result, while gold ounces produced but not delivered increased by 5,812oz (or 8.4%) over the quarter, to 75,291oz, silver ounces produced but not delivered decreased by more than a third to just 1.3Moz.
Consequently, we calculate that gold and silver ounces produced but not yet delivered as at end-June now amount to 2.67 and 0.79 months of full-year production (cf 2.43 and 2.03 months as at end-Q123 previously), respectively, and compare with WPM’s target levels of two to three months for gold and palladium and two months for silver (see below).
|
Exhibit 4: WPM ounces produced but not yet delivered, Q316–Q223 (months of production) |
|
|
Source: Edison Investment Research, WPM. Note: As reported. |
General and administrative expenses
At the time of its Q422 results, WPM provided guidance for non-stock general and administrative (G&A) expenses of US$47–50m or US$11.75–12.50m per quarter for FY23 (cf US$47–49m in FY22, US$42–44m in FY21 and US$40–43m in FY20), including all employee-related expenses, charitable contributions, etc, but excluding performance share units (PSU) and equity settled stock-based compensation. In the event, at US$12.2m, non-stock G&A expenses in Q123 were towards the middle of the range implied by WPM’s official guidance:
Exhibit 5: WPM general and administrative expenses, Q221–Q223 (US$000s)
Item |
Q221 |
Q321 |
Q421 |
FY21 |
Q122 |
Q222 |
Q322 |
Q422 |
FY22 |
Q123 |
Q223 |
G&A salaries excluding PSU* and equity settled stock-based compensation |
4,634 |
4,283 |
4,618 |
18,244 |
5,345 |
5,061 |
4,629 |
4,187 |
19,222 |
5,021 |
4,749 |
Other (inc. depreciation, donations and professional fees) |
5,852 |
5,173 |
6,818 |
23,475 |
4,871 |
5,784 |
5,137 |
7,112 |
22,905 |
6,456 |
7,407 |
Non-stock based G&A |
10,486 |
9,456 |
11,436 |
41,719 |
10,216 |
10,845 |
9,766 |
11,299 |
42,127 |
11,477 |
12,156 |
Guidance |
10,500–11,250 |
10,500–11,250 |
11,717–13,717 |
42,000–44,000 |
11,750–12,250 |
11,750–12,250 |
11,750–12,250 |
11,750–12,250 |
47,000-49,000 |
11,750-12,500 |
11,750-12,500 |
PSU* accrual |
6,672 |
2,824 |
4,203 |
14,004 |
8,560 |
110 |
(1,491) |
7,035 |
14,214 |
5,855 |
2,625 |
Equity settled stock-based compensation |
1,307 |
1,315 |
1,315 |
5,262 |
1,342 |
1,498 |
1,568 |
1,439 |
5,846 |
1,542 |
1,859 |
Stock-based G&A |
7,979 |
4,139 |
5,518 |
19,266 |
9,902 |
1,608 |
77 |
8,474 |
20,060 |
7,397 |
4,484 |
Total general & administrative |
18,465 |
13,595 |
16,954 |
60,985 |
20,118 |
12,453 |
9,843 |
19,773 |
62,187 |
18,874 |
16,640 |
Total/Non-stock based G&A (%) |
+76.1 |
+43.6 |
+48.3 |
+46.2 |
+96.9 |
+14.8 |
+0.8 |
+75.0 |
+47.6 |
+64.5 |
+36.9 |
Source: WPM, Edison Investment Research. Note: *Performance share units. Totals may not add up owing to rounding.
Given the performance of WPM’s shares during the quarter, stock-based G&A expenses in Q223 were well within the error of estimation implied by the regression analysis between the two (as shown in Exhibit 6, below):
|
Exhibit 6: Graph of historical share price move (US$/share) versus quarterly stock-based G&A expenses, Q419–Q223 |
|
|
Source: Edison Investment Research (underlying data: Bloomberg and Wheaton Precious Metals) |
The analysis of stock-based G&A expenses over the past 15 quarters relative to the change in WPM’s share price (also in US dollars) continues to exhibit a close Pearson product-moment (correlation) coefficient between the two of 0.78, which remains statistically significant at the 5% level for a directional hypothesis (ie there is less than a 5% probability that this relationship occurred by random chance) and this therefore continues to remain the basis of our quarterly and full-year forecasts for G&A expenses in Exhibit 8.
FY23 and five-year and 10-year guidance
At the time of its 21 February production and sales announcement, Wheaton also provided detailed production guidance for FY23 (for the first time), as well as for the five years from FY23–27 (inclusive) and the 10 years from FY23–32 (inclusive). These remain unchanged and compare with Edison’s forecasts over the equivalent periods, as follows:
Exhibit 7: WPM precious metals production – Edison forecasts cf guidance
FY23e |
FY23–27 average* |
FY23–32 average |
|
Previous Edison forecast |
|||
Silver production (Moz) |
19.8 |
||
Gold production (koz) |
335.8 |
||
Cobalt production (klb) |
655 |
||
Palladium production (koz) |
15.0 |
||
Gold equivalent (koz) |
613.5 |
803 |
818 |
Current Edison forecast |
|||
Silver production (Moz) |
19.3 |
||
Gold production (koz) |
338.4 |
||
Cobalt production (klb) |
683 |
||
Palladium production (koz) |
15.3 |
||
Gold equivalent (koz) |
610.6 |
802 |
818 |
WPM guidance |
|||
Silver production (Moz) |
20.0–22.0 |
||
Gold production (koz) |
320–350 |
||
Cobalt & palladium production (koz AuE) |
22–25 |
||
Gold equivalent (koz) |
600–660 |
810 |
850 |
Source: WPM, Edison Investment Research forecasts. Note: *Edison forecasts include Salobo III from FY23, Rosemont/Copper World from FY27 and Antamina extension from FY28.
WPM’s updated five-year and 10-year guidance is based on standardised pricing assumptions of US$1,850/oz gold, US$24.00/oz silver, US$1,800/oz palladium and US$18.75/lb cobalt. Of note in this context is an implied gold/silver ratio of 77.1x, which compares with its current ratio of 84.2x, but a long-term average of 61.5x (since gold was demonetised in August 1971). At the standardised prices indicated, our gold equivalent production forecast of 610.6koz gold equivalent (AuE) for FY23 self-evidently lies well within WPM’s guidance range of 600–660koz AuE.
Otherwise, readers will note that Edison’s medium-term production forecasts are within 1% of WPM’s guidance for the period FY23–27 and within 4% of its longer-term guidance for FY23–32, which we regard as an acceptable range of variance, given the time horizons involved. Note that both Edison’s and Wheaton’s estimates necessarily exclude potential future stream acquisitions (of which there are likely to be a number over the timeframe indicated).
Growth opportunities
Short-term opportunities
Constancia
Although Constancia experienced both lower throughput and grades relative to the prior year period in Q223, as per Hudbay’s recent earnings releases, full mining activities have resumed in the Pampacancha pit since February. Output was adversely affected by a period of higher stripping in Q223. However, we are now anticipating that gold production attributable to Wheaton from Constancia will increase by in excess of 75% in Q3 and Q4 compared with Q2 to c 13,000–15,000oz per quarter.
San Dimas
Since First Majestic’s acquisition of Primero in January 2018, it has been developing a long-term mine and mill optimisation plan for San Dimas, including:
■
an additional leach tank with safety screen,
■
modernisation of the general plant control and monitoring capabilities,
■
debottlenecking and optimisation of the crushing circuit for consistent operation,
■
upgrading the tailings filtration plant,
■
modernisation of the Merrill-Crowe and smelting operations,
■
an estimated 40% reduction in ore drive development dimensions allowing for reduced dilution and reductions in costs associated with standard ground support, and
■
pillar recoveries from the Tayoltita, Santa Rita and Noche Buena mines to add a further c 300tpd (12%) to throughput.
Other
Production of palladium and gold at Stillwater (operated by Sibanye-Stillwater) will increase under the influence of the Fill-the-Mill project at East Boulder as well as the Blitz project scheduled for FY24. Similarly, the Voisey’s Bay underground project is in the process of ramping up to full production.
Medium-term opportunities
In the medium term, Wheaton has six projects that are progressing on their route to production:
■
In November 2022, Aris Mining released the results of the Marmato Lower Mine expansion pre-feasibility study, involving the development of a new underground mine and a 4,000tpd ore processing facility to add to the existing 1,250tpd Marmato Upper Mine and, on 12 July 2023, announced that it had received approval from Colombia’s Corporación Autónoma Regional de Caldas for its Environmental Management Plan, which permits the go-ahead of the Marmato Lower Mine. The Lower Mine project is estimated to cost c US$280m in initial capex and tender bids for key long lead procurement items such as mills, crushers, feeders, thickeners, the oxygen plant, gold room and filters are already reported to be in the market. Orders are in the process of being placed and the new 4,000tpd mill is scheduled for mechanical completion in Q325.
■
On 16 May 2023, Wheaton announced the purchase of a stream from Lumina’s Cangrejos project in Ecuador. Under the terms of the stream, WPM will pay Lumina a total upfront cash consideration of US$300m in tranches, in return for 6.6% of the payable gold from the project until 700,000oz gold have been delivered, whereupon the stream will be reduced to 4.4% of the payable gold production for the life of the mine. Attributable production from the mine is forecast to average over 24,000oz gold pa for the first 10 years of production and over 24,500oz gold pa for the full 26-year life of the mine. WPM will make ongoing payments for the gold ounces delivered equal to 18% of the spot price of gold until the uncredited deposit is reduced to nil and 22% of the spot price of gold thereafter. For the purposes of our modelling, we have assumed that first production from the Cangrejos mine will occur in FY29. In the meantime, Lumina has recommenced drilling at the project, initiating both geotechnical and infill resource definition programmes, which it expects to complete in Q124, with the aim, inter alia, of converting probable mineral reserves to proven status, financed via its early deposit precious metals purchase agreement (PMPA) with WPM. Drilling will also produce fresh material for the next round of metallurgical test work to support its ongoing full feasibility study.
■
B2Gold has confirmed that site construction at Goose is ongoing and that the project’s first ice road has successfully transported all of the materials required to complete building envelopes in 2023. As such, the project remains on schedule for mill completion in Q125. In the meantime, B2Gold is initiating an exploration program to further define untapped potential and unlock further opportunities for growth. Plans for underground mining development have been accelerated to increase average gold production to over 300koz pa in the first five years of mining. Underground mining is also now scheduled to mine and backfill the full Umwelt crown pillar earlier in the mine life, which is expected to contribute a further c 150koz of gold production to the life of mine plan.
■
On 9 March, Artemis received its last major permit ahead of major construction work for its Blackwater mine in the form of a BC Mines Act Permit. It also closed the associated US$385m project loan facility. Subsequently, in May, it reported that site works were underway with over 280 hectares logged and cleared including priority infrastructure areas such as the mine haul road network and water management structures. Where required, the existing road network has also been upgraded to allow access for heavy construction equipment to key infrastructure locations. A laydown area has been completed to accommodate the construction fleet, maintenance facilities and construction offices and a construction camp has been completed, including the installation and commissioning of a wastewater treatment plant, expanding the site capacity to 420 people. The initial fleet is expected to be delivered in Q423 and to be ‘shovel ready’ in H224. On 4 July, Artemis announced receipt of the Fisheries Act Authorization for development of Blackwater, which will facilitate the commencement of construction of water diversion structures and dams in the Davidson Creek valley, which runs through the basin of the Blackwater tailings storage facility. On 14 June, Wheaton amended its Blackwater Gold PMPA with Artemis. Under the terms of the amended agreement, Wheaton is now entitled to purchase an amount of gold equal to 8% of the payable gold production until 464,000oz have been delivered (cf 279,908oz previously), with this threshold to increase should there be a delay in the anticipated timing of deliveries. Once the threshold has been achieved, WPM’s attributable gold production will drop to 4% of payable gold production – now estimated by Edison to be in FY40 cf FY35 previously – for the life of the mine. In exchange for the amendment, Wheaton has committed to pay an additional upfront cash consideration of US$40m, payable in four instalments, with the first payment of US$10m having been made on 15 June. In conjunction with this amendment, Artemis announced that it is to commit to additional investment as part of its Phase 1 development to facilitate the potential fast-tracking of its Phase 2 expansion. After a brief hiatus in July on account of the wildfires in British Columbia, Artemis announced that it had returned to full construction on 3 August.
■
In November, Generation Mining received the final environmental approvals for its Marathon palladium-copper project in northern Ontario. In March, it released the results of an updated feasibility study showing an after tax NPV6 of C$1.16bn and a project internal rate of return of 26%, ahead of executing a mandate letter to arrange a senior secured project finance facility of up to US$400m to fund the construction and development of the project (a key milestone). This year, it is aiming to secure key provincial permits, related to species at risk, tree harvesting and water quality, etc, so that early construction works can commence. The start of construction is anticipated imminently and production in Q3–Q425, to which end it has already purchased an unused surplus SAG mill and a ball mill.
■
Adventus Mining signed the investment contract for the Curipamba project with the Ecuadoran government in December. To date in 2023, it has advanced detailed engineering and procurement activities and completed the first of two phases of the required environmental and social impact assessment (ESIA), managed and overseen by the government. However, on 1 August, the Constitutional Court of Ecuador admitted for processing an unconstitutionality claim filed by the indigenous group CONAIE and other plaintiffs against Presidential Decree 754, which was signed by the president of Ecuador on 31 May, that regulates environmental consultation for all public and private industries and sectors in Ecuador – not limited to the metals and mining sector. As a result, the Constitutional Court ordered the provisional suspension of the Decree until it can resolve the claim, which will require the government of Ecuador to present argument, within 15 working days, to evidence the constitutionality of the Decree for the consideration of the Constitutional Court. The immediate effect of the suspension is that no medium- or high-impact projects, from any sector or industry in the country, including the Curipamba project, will be able to obtain an environmental licence until the Constitutional Court resolves the issue. The government of Ecuador has stated that it will employ all measures at its disposal to respond to the Constitutional Court. In the meantime, the Adventus Mining management team reports that it has identified, and continues to evaluate, several significant improvements to the project that are expected ‘to improve project economics inclusive of cost inflation factors’.
Long-term opportunities
Salobo
On 24 October 2018, Vale announced the approval of the Salobo III brownfields mine expansion, intended to increase processing capacity at Salobo from 24Mtpa to 36Mtpa, with start-up at that point scheduled for H222 and an estimated ramp-up time of 15 months. According to its agreement with Vale at the time, depending on the grade of the material processed, WPM was to have made a payment to Vale for this expansion, subject to a 90-day completion test, which WPM estimated was to have been in the range US$550–670m in FY23–25, in return for which it was to be entitled to its full 75% attributable share of expanded gold production.
After the end of Q422 however, Wheaton and Vale agreed to amend the Salobo PMPA to adjust the expansion payment terms to provide increased flexibility for the ramp-up of the expansion, while also maintaining an incentive for Vale to maximise grade on an annual basis. The expansion payment will now be phased, with Wheaton making an initial payment once actual throughput is expanded above 32Mtpa and a second payment if actual throughput is expanded above 35Mtpa by 1 January 2031. The total cumulative payments will range from US$283m to US$552m, dependent on Vale’s timing for each of the production increases. Where before Edison had been forecasting that Wheaton would make the whole payment (of US$530m) in FY24, owing to the successful nature of the ramp-up of the Salobo III project to date in FY23 (it contributed 30.9% of total Salobo copper production in Q223 cf an expected 33.3% pro-rata to throughput at full capacity), we are now forecasting that it will make the whole payment (of US$552m) in FY23. In addition, Wheaton will be required to make annual payments of between US$5.1m and US$8.5m for a 10-year period following payment of the expansion payments if the Salobo mine maintains a high-grade mine plan.
These payments compare to WPM’s purchase of a 25% stream from Salobo in August 2016 for a consideration of US$800m (see our note Going for gold, published on 30 August 2016), the US$900m it paid for a similar stream in March 2015 (when the gold price averaged US$1,179/oz) and the US$1.33bn it paid for its original 25% stream in February 2013.
According to Vale, the project successfully commenced at the end of 2022 and is expected to achieve full capacity in FY24. Once full capacity at Salobo III has been completed, however, WPM believes that reserves and resources at the mine could support a further 33% capacity increase, from 90ktpd to 120ktpd (denoted Salobo IV). Notwithstanding its long-term underground potential, WPM believes such an expansion could be supported by open-pit mining alone. Under the terms of its agreement with Vale, there would be no additional payment due from WPM in respect of the Salobo IV expansion.
Rosemont/Copper World
Rosemont/Copper World is in the vicinity of a number of large porphyry-type producing copper mines and will be one of the largest copper mines in the United States, with initial output of c 86,000t copper per year from mined sources (c 8% of total US copper production), rising to c 101,000tpa after 16 years. Total byproduct production of silver attributable to WPM is estimated to be c 1.7Moz Ag pa for Phase I, followed by c 2.4Moz Ag pa for Phase II.
The evolution of the project from Rosemont to Copper World
In March 2019, Rosemont/Copper World’s operator, Hudbay, received both a Mine Plan of Operations from the US Forest Service and a Section 404 Water Permit from the US Army Corps of Engineers (ACOE), which was effectively the final material administrative step before the Rosemont mine could start development. Subsequently, Hudbay indicated it would seek board approval to start construction work by the end of CY19, which would have enabled first production ‘by the end of 2022’. In the meantime, it started early works to run concurrently with financing activities (including a potential joint venture partner).
A legal challenge, lunched in July 2019, has since delayed the project. However, Hudbay has continued to explore in and around the area of the mine and, on 22 September 2021, announced the intersection of additional high-grade copper sulphide and oxide mineralisation predominantly located on its wholly owned patented mining claims (denoted Copper World). To date, seven deposits have been identified at Copper World with a combined strike length of over 7km and, on 15 December 2021, Hudbay announced a maiden mineral resource at Copper World of 272Mt in the indicated category and 142Mt in the inferred category, both at an average grade of 0.36% copper. The mineralisation consists of both skarn and porphyry copper sulphides with a significant oxidised component along a regional fault along the west side of the Rosemont, Bolsa and Broad Top Butte deposits known as the Backbone Fault. As a consequence, it was determined that approximately 33Mt of inferred mineral resources at the Bolsa deposit, which were previously considered to be waste in the resource pit shell used for Rosemont’s NI 43–101 feasibility study, could now potentially be converted into reserves, which would result in less waste being mined at Rosemont, thereby reducing costs and energy consumption per tonne of ore mined. In addition, the Rosemont deposit also contains oxide mineralisation that was previously classified as waste, which could be processed with the oxide mineralisation at Copper World, and it is expected that further synergies will be identified as Hudbay explores the gap between Bolsa and Rosemont. Note that the Copper World discovery is included in WPM’s area of interest under its PMPA with Hudbay.
A new development plan
As a result of these discoveries, Hudbay has adjusted its plan to develop the district. Among other things, it has now acquired a private land package totalling approximately 4,500 acres to support an operation on private lands. The initial technical studies for Copper World were incorporated into a preliminary economic assessment (PEA) investigating the development of the Copper World deposits in conjunction with an alternative plan for the Rosemont deposit, which was announced to the market on 8 June 2022, and proposed a two-phase mine development plan. The first phase of the mine plan requires only state and local permits and demonstrates an approximate 16-year mine life. The second phase then extends the mine life to 44 years and incorporates an expansion onto federal lands to mine the entire Rosemont and Copper World deposits. The second phase of the mine plan will be subject to the federal permitting process and the company expects that it will be able to pursue the federal permits within the constraints imposed by the courts’ most recent legal decisions if any subsequent appeals are not successful.
On 24 May 2022, Hudbay received a favourable decision from the US District Court for the District of Arizona on all issues relating to the development of Copper World, including that Copper World and Rosemont are not connected under the National Environmental Policy Act (NEPA) and, therefore, that the ACOE does not have an obligation to include Copper World as part of its NEPA review of Rosemont. The District Court also granted Hudbay’s motion to dismiss the Copper World preliminary injunction request filed by the plaintiffs in the two lawsuits challenging the Section 404 Clean Water Act permit for Rosemont on the basis that the lawsuits were moot after the company surrendered its 404 permit back to the ACOE in April 2022. Within this context, the ACOE has never determined that there are jurisdictional waters of the United States on the Copper World site and Hudbay has independently concluded through its own scientific analysis that there are no such waters in the area. In this respect, Hudbay believes the District Court’s decision, together with the 12 May 2022 decision, clarifies the permitting path for Copper World, including the requirements to receive federal permits for the second phase only (ie years 16 to 44 of the project) under existing mining regulations and no requirement for a 404 (water) Permit. In May, Hudbay also received a favourable ruling from the US Court of Appeals for the Ninth Circuit that reversed the US Fish and Wildlife Service’s designation of the area near Copper World and the former Rosemont project as jaguar critical habitat. While this ruling does not affect the state permitting process for Phase I of Copper World, it is expected to simplify the federal permitting process for Phase II of the project. In the meantime, Hudbay continues to expect to receive the two remaining state permits required (an Aquifer Protection Permit and an Air Quality Permit) in H223.
PEA completed and PFS underway ahead of potential project sanctioning in 2024
Resources were reported to have expanded materially to 792Mt in the measured category, 381Mt in the indicated category and 262Mt in the inferred category at the time of Hudbay’s PEA at an average grade of 0.40% copper. In April 2022, the company commenced early works at Copper World with initial grading and clearing activities at site and, in January, it received an approved right-of-way from the Arizona State Land Department that will allow for infrastructure such as roads, pipelines and powerlines to connect the properties in the company’s private land package. Shortly afterwards, it also announced the receipt of confirmation from the Army Corps of Engineers that its previous surrender of the Section 404 Clean Water Act permit for the former Rosemont project had been formally accepted and revoked, as requested.
Clearing and grading work to prepare for the Copper World site, including the construction of roads and other facilities, is underway. In the meantime, pre-feasibility activities for the private land Phase I of the Copper World project are reported to be well-advanced and a pre-feasibility study is expected to be released in Q323. Among other things, this will focus on converting the remaining inferred mineral resources to measured and indicated status and the evaluation of many of the project’s optimisation and upside opportunities. It will then complete a definitive feasibility study as well as receiving all required state and local permits over the next 12 months, while simultaneously evaluating a variety of financing options, including a potential minority joint venture partner, prior to project sanction potentially as early as 2024. As such, Edison is continuing to forecast production from Rosemont/Copper World attributable to WPM from FY27. However, readers should note that any acceleration in the process of being granted federal permits could allow Hudbay earlier access to higher-grade areas of the orebody, especially at Rosemont. In the meantime, it is continuing exploration and technical work at site to support its feasibility studies.
Antamina
In April 2022, Antamina announced a US$1.6bn investment that will lengthen the mine’s useful life from 2028 to 2036. Currently, the mine is carrying out a third and final ‘public participation’ with residents of the northern Andean region of Ancash, where the mine is located, and is awaiting a response from the local authority, Senace, regarding the company’s request to modify its environmental impact assessment to allow the mine to extend its operating life by eight years. Production and the mine’s operational footprint would remain the same and it hopes to achieve mine extension approval this year. The mine, which is co-owned by Glencore, BHP, Teck and Mitsubishi Corp, is Peru’s largest, and the world’s second-largest, copper mine.
Pascua-Lama
WPM’s contract with Barrick provided for a completion test that, if unfulfilled by 30 June 2020, would result in WPM being entitled to the return of its upfront cash consideration of US$625m less a credit for any silver delivered up to that date from three other Barrick mines (at which point it would have no further streaming interest in the mine). Given the test was unfulfilled, WPM had the right to an estimated US$252.3m (WPM’s carrying value of Pascua-Lama) repayment from Barrick in FY20. Given the long-term optionality provided by the Pascua-Lama project, however, WPM instead opted not to enforce the repayment of its entitlement and to maintain its streaming interest in the project (which was originally expected to deliver an attributable 1.7–12.0Moz silver pa, averaging 5.2Moz Ag pa, to WPM at a cost of US$3.90/oz inflating at 1% per year).
A Chilean court ordered Pascua-Lama to close in 2020. However, Barrick is advancing a high-level study into the project, which is thought to be nearing completion. The study is understood to be focusing on the fact that a substantial portion of the resource could be processed by leaching or agitated leaching, which would require only modest modifications to the circuit already built. This raises the possibility that the orebody could be developed in a different manner and Barrick’s goal is to demonstrate a viable project to both the Chilean and Argentinian governments. If successful, it would then pursue permitting options (and, in particular, water permits) and build out a new model for the project’s development, in which case an investment decision on Pascua-Lama could be made as early as 2024.
Other potential future growth opportunities
Wheaton reports that its development team remains ‘exceptionally busy’ evaluating new opportunities. In general, WPM expects to be conducting due diligence processes on approximately 10–12 projects at any one time, which it expects to narrow to three to four target projects over approximately 12 months. Most of the opportunities currently being evaluated by WPM are reported to be the precious metal by-product streams of base metal mines, although there are also reported to be some high-margin, purely precious metals mines included in the evaluation process. In the first instance, WPM would fund any such transactions via the US$2bn available under its revolving credit facility, plus the US$828.8m in cash that it has on its balance sheet (at end-Q223) and, potentially, its US$300m at-the-market equity programme.
While it is difficult, or impossible, to predict potential future stream acquisition targets with any degree of certainty, it is possible to highlight two that may be of interest to WPM in due course for which it already has strong, existing counterparty relationships, being:
■
the platinum group metal by-product stream at Sudbury (operated by Vale), and
■
the 30% of the gold output at Constancia (operated by Hudbay) that is not currently subject to any streaming arrangement.
FY23 guidance and forecasts
In formulating our quarterly forecasts for WPM for Q323 and for the remainder of the year, we have reduced our gold price for the remainder of the year by 2.1%, from US$1,955/oz to US$1,914/oz and our silver price by 8.3%, from US$24.79/oz to US$22.74/oz, while increasing our palladium price by 2.8% – all to reflect currently prevailing prices. We have also honed our production and sales forecasts for Zinkgruvan, Neves-Corvo and Sudbury (albeit immaterially). As a consequence, our Q323, Q423 and FY23 full financial forecasts are now as follows:
Exhibit 8: WPM FY23 forecast, by quarter*
US$000s |
Q123 |
Q223 |
Q323e |
Q323e |
Q423e |
Q423e |
FY23e |
FY23e |
Silver production (koz) |
4,927 |
4,417 |
4,358 |
4,222 |
5,851 |
5,732 |
19,299 |
19,771 |
Gold production (oz) |
73,037 |
85,083 |
88,406 |
85,790 |
97,884 |
94,482 |
338,392 |
335,776 |
Palladium production (koz) |
3,705 |
3,880 |
3,871 |
3,871 |
3,871 |
3,871 |
15,327 |
14,961 |
Cobalt production (klb) |
124 |
152 |
204 |
204 |
204 |
204 |
683 |
655 |
Silver sales (koz) |
3,749 |
4,437 |
3,756 |
3,391 |
5,589 |
5,344 |
16,921 |
17,278 |
Gold sales (oz) |
62,605 |
75,294 |
82,439 |
79,999 |
97,863 |
94,462 |
312,359 |
314,213 |
Palladium sales (oz) |
2,946 |
3,392 |
3,483 |
3,483 |
3,856 |
3,856 |
13,676 |
13,445 |
Cobalt sales (klb) |
323 |
265 |
204 |
204 |
204 |
204 |
995 |
854 |
Avg realised Ag price (US$/oz) |
22.85 |
24.13 |
24.57 |
23.25 |
24.79 |
22.74 |
23.23 |
24.18 |
Avg realised Au price (US$/oz) |
1,904 |
1,986 |
1,951 |
1,927 |
1,955 |
1,914 |
1,933 |
1,949 |
Avg realised Pd price (US$/oz) |
1,607 |
1,438 |
1,264 |
1,285 |
1,265 |
1,301 |
1,397 |
1,382 |
Avg realised Co price (US$/lb) |
15.04 |
13.23 |
15.16 |
15.16 |
15.16 |
15.16 |
14.60 |
15.06 |
Avg Ag cash cost (US$/oz) |
5.07 |
5.01 |
5.53 |
5.35 |
5.30 |
5.14 |
5.13 |
5.28 |
Avg Au cash cost (US$/oz) |
496 |
461 |
441 |
442 |
439 |
440 |
456 |
455 |
Avg Pd cash cost (US$/oz) |
294 |
261 |
228 |
231 |
228 |
234 |
253 |
250 |
Avg Co cash cost (US$/lb) |
3.30 |
3.20 |
2.73 |
2.73 |
2.73 |
2.73 |
3.04 |
2.93 |
Sales |
214,465 |
264,972 |
260,622 |
240,578 |
337,829 |
310,420 |
1,030,435 |
1,061,450 |
Cost of sales |
||||||||
Cost of sales, excluding depletion |
51,964 |
58,642 |
58,481 |
54,835 |
74,032 |
70,469 |
235,910 |
239,964 |
Depletion |
45,000 |
54,474 |
52,909 |
50,779 |
67,699 |
65,258 |
215,511 |
214,634 |
Total cost of sales |
96,964 |
113,116 |
111,390 |
105,614 |
141,731 |
135,727 |
451,421 |
454,598 |
Earnings from operations |
117,501 |
151,856 |
149,232 |
134,964 |
196,098 |
174,694 |
579,015 |
606,852 |
Expenses and other income |
||||||||
– General and administrative** |
18,874 |
16,640 |
18,042 |
17,875 |
17,396 |
17,525 |
70,914 |
69,592 |
– Foreign exchange (gain)/loss |
0 |
0 |
||||||
– Net interest paid/(received) |
1,378 |
1,352 |
1,454 |
1,454 |
1,454 |
1,454 |
5,639 |
5,741 |
– Other (income)/expense |
(7,387) |
(8,811) |
(7,192) |
-8,431 |
(7,150) |
-7,352 |
-31,981 |
(29,697) |
Total expenses and other income |
12,865 |
9,182 |
12,304 |
10,898 |
11,700 |
11,627 |
44,571 |
45,635 |
Earnings before income taxes |
104,636 |
142,675 |
136,928 |
124,066 |
184,398 |
163,066 |
534,443 |
561,217 |
Income tax expense/(recovery) |
205 |
91 |
250 |
250 |
250 |
250 |
796 |
955 |
Marginal tax rate (%) |
0.2 |
0.1 |
0.2 |
0.2 |
0.1 |
0.2 |
0.1 |
0.2 |
Net earnings |
104,431 |
142,584 |
136,678 |
123,816 |
184,148 |
162,816 |
533,647 |
560,262 |
Average no. shares in issue (000s) |
452,370 |
452,892 |
452,838 |
452,892 |
452,838 |
452,892 |
452,762 |
452,721 |
Basic EPS (US$) |
0.231 |
0.315 |
0.302 |
0.273 |
0.407 |
0.360 |
1.18 |
1.24 |
Diluted EPS (US$) |
0.230 |
0.314 |
0.301 |
0.273 |
0.405 |
0.359 |
1.18 |
1.23 |
DPS (US$) |
0.15 |
0.15 |
0.15 |
0.15 |
0.15 |
0.15 |
0.60 |
0.60 |
Source: WPM accounts, Edison Investment Research. Note: *Excluding impairments, impairment reversals and exceptional items (except where indicated). **Forecasts now include stock-based compensation costs. Totals may not add up owing to rounding.
Our updated adjusted basic EPS forecast of US$1.18 per share for FY23 compares with the market, as follows:
Exhibit 9: WPM FY23 consensus EPS forecasts (US$/share), by quarter
Q123 |
Q223e |
Q323e |
Q423e |
Sum Q1–Q423e |
FY23e |
|
Edison forecasts |
0.231 |
0.315 |
0.273 |
0.360 |
1.179 |
1.180 |
Mean consensus |
0.231 |
0.315 |
0.319 |
0.337 |
1.202 |
1.159 |
High consensus |
0.231 |
0.315 |
0.390 |
0.405 |
1.341 |
1.320 |
Low consensus |
0.231 |
0.315 |
0.270 |
0.270 |
1.086 |
1.050 |
Source: Refinitiv, Edison Investment Research. Note: As at 10 August 2023.
Valuation
Absolute
WPM is a multi-asset company that has shown a willingness and desire to buy streams in the past to maintain production and maximise shareholder returns (most recently over Lumina’s Cangrejos mine in south-west Ecuador). As a result, rather than our customary method of discounting maximum potential dividends over the life of operations back to FY23, in the case of WPM (as with Newmont and Endeavour), we discount forecast cash flows back over four years from the start of FY23 and then apply an ex-growth terminal multiple to forecast cash flows in that year (ie FY26) based on an appropriate discount rate.
Compared with our previous estimates, our forecast for pre-financing cash flow has reduced in FY23 as a result of our assumption that Wheaton will now pay its full commitment for Salobo III of US$552m in FY23 (cf US$530m in FY24 previously). However, our pre-financing cash flow estimate for FY24 has increased commensurately and our estimate of WPM’s ‘terminal’ pre-financing cash flow in FY26 is, to all intents and purposes, unchanged, at US$2.65 per share, as shown below:
|
Exhibit 10: WPM cash flow per share and related valuation (US$/share), FY23–26 |
|
|
Source: Edison Investment Research. Note: Valuation line assumes cash flow per share growth rate of 4% pa post-FY26 in nominal terms, which equals the average US rate of CPI inflation since 1972 (ie 0% pa growth in real terms). |
Assuming 4% growth in nominal cash flows beyond FY26 (ie 0% growth in real cash flows) and applying a discount rate of 9% (being the expected long-term required nominal equity return), our ‘terminal’ valuation of the company at end-FY26 is US$54.88 per share (cf US$54.92/share previously), or C$73.76 per share. However, it should be noted that this valuation is inherently conservative in that it assumes zero growth in (real) cash flows beyond FY26. This is inconsistent with the gold price, which has risen at a compound average annual growth rate of 7.4% per year from 1967 to 2022 and at a simple average annual growth rate of 9.6% per year (cf a compound average inflation rate over the same period of 4%).
|
Exhibit 11: Gold price annual performance, 1968–2022 |
|
|
Source: Edison Investment Research (underlying data: US Bureau of Labor Statistics, Bloomberg, kitco.com, South African Chamber of Mines) |
It is also inconsistent with WPM’s longer-term historical performance, wherein operational cash flows have increased at a compound average annual growth rate of 21% pa for the 17 years between FY05 and FY22, while its operational cash flows per share have increased at compound average annual growth rate of 14.1% pa.
Historical
Excluding FY04 (part-year), WPM’s shares have historically traded on an average P/E multiple of 30.4x current year basic underlying EPS, excluding impairments (cf 37.4x Edison or 38.2x Refinitiv consensus FY23e currently – see Exhibit 12).
|
Exhibit 12: WPM’s average historical current year P/E multiples, 2005–22 |
|
|
Source: average share price data Bloomberg, Edison Investment Research calculations |
Applying this 30.4x multiple to our (ostensibly unchanged) EPS forecast of US$1.87 in FY26 implies a potential value per share for WPM of US$56.71 (cf US$56.77 previously) or C$76.23 in that year.
Relative
From a relative perspective, it is notable that WPM is cheaper than its peers on at least 63% (23 out of 36) of the valuation measures observed in Exhibit 13 if Edison estimates are used or 50% (18 out of 36) of the same valuation measures if consensus forecasts are used.
Exhibit 13: WPM comparative valuation versus a sample of operating and royalty/streaming companies
P/E (x) |
Yield (%) |
P/CF (x) |
|||||||
Year 1 |
Year 2 |
Year 3 |
Year 1 |
Year 2 |
Year 3 |
Year 1 |
Year 2 |
Year 3 |
|
Royalty companies |
|||||||||
Franco-Nevada |
38.7 |
35.3 |
37.1 |
0.9 |
1.0 |
1.0 |
27.3 |
25.4 |
26.4 |
Royal Gold |
30.5 |
25.7 |
24.3 |
1.2 |
1.2 |
1.1 |
17.3 |
15.2 |
14.7 |
Sandstorm Gold |
54.3 |
49.2 |
39.3 |
1.1 |
1.1 |
1.1 |
12.7 |
13.3 |
11.6 |
Osisko |
32.9 |
31.8 |
28.2 |
1.2 |
1.2 |
1.2 |
18.2 |
17.5 |
16.8 |
Average |
39.1 |
35.5 |
32.2 |
1.1 |
1.1 |
1.1 |
18.9 |
17.9 |
17.4 |
WPM (Edison forecasts) |
37.4 |
29.9 |
24.6 |
1.4 |
1.5 |
1.7 |
26.1 |
19.3 |
16.8 |
WPM (consensus) |
38.2 |
32.6 |
32.8 |
1.3 |
1.1 |
1.3 |
27.2 |
22.3 |
22.4 |
Implied WPM share price (US$)* |
46.04 |
52.33 |
57.87 |
54.30 |
56.91 |
67.91 |
31.88 |
40.77 |
45.61 |
Source: Refinitiv, Edison Investment Research. Note: Peers priced on 10 August 2023. *Derived using Edison forecasts and average consensus multiples.
Stated alternatively, were WPM to trade at the average multiples of its peers, we calculate that its share price should be US$50.40, or C$67.75 currently, on the basis of Edison’s financial forecasts.
In this context, we note that, whereas Edison’s financial forecasts for Wheaton in years one to three imply improving profitability (based on improving volumes of production and sales superimposed on broadly flat metals prices), consensus forecasts appear to imply a much flatter profitability profile, suggesting that either the market is assuming smaller increases in volumes or a simultaneous decrease in metals prices.
Research: Industrials
Arctic Paper’s H123 results reflect dampened demand, with customer destocking, alongside sequential price declines seen across the entirety of the European paper and pulp market. Deliveries of its products were substantially below estimated end-use demand, and global commodity prices, such as for pulp and energy, fell from historical highs to cyclical lows in the six-month period. Despite a weaker H123 versus a record strong comparator, Arctic has maintained a robust balance sheet enabling it to continue its diversification into the higher-margin energy and packaging markets and move up the value chain.